Animal Shelter – Kennel HVAC Modifications

03/24/21 – AKM requests SOSS for the installation of mini-split HVAC systems for (2) kennels. TEI is authoring and will submit by end of the day 03/26/21.
04/28/21 – SOSS submitted. Project completion pending SOSS approval.
05/26/21 – TEI receives signed SOSS and PO. TEI completes drawings and submits to IBI for Plan review. Plan review approved and TEI applies for permit. Installation work to be coordinate with Trades and building manager.
06/23/21 – Permits received. Work installed. Upon repair of boards in the units (due to pest infestation, electronics were compromised), final inspections will occur.
07/28/21 – Repairs have been completed and ready for TEI to call IBI and Schedule a final. TEI coordinating with Trades and IBI and will schedule in the next few days.
08/26/21 – IBI final inspection scheduled for 08/27/21. Time TBD, per IBI standards, must call day of the inspection to get timing. TEI coordinating with John Kleeman and John Nester.
10/26/21 – IBI required to have HVAC permit prior to the final for IBI. TEI developed HVAC documents and are awaiting permit approval and inspection to re-schedule the IBI final.
12/13/21 – Plan review and zoning have verbally approved.  TEI was told full approval for the HVAC permit will be approved on 12/17/21.  Once approved and picked up, we can have inspection, approval, and then have IBI final inspection.
01/25/22 – HVAC plans approved.  Need to schedule final HVAC inspection and also final IBI
02/23/22 – Per building manager – 3 out of 4 units not functioning currently due to rodent issues.   building manager will contact TEI when the units are operational so that we can schedule the finals.
04/27/22 – inspections pending units being operational.
05/26/22 – HVAC inspection complete/passed.  IBI pending repairs to work by NK heating and Air.  Building manager to notify TEI when we can schedule final.
06/28/22 – IBI pending repairs to work by NK heating and Air.  Building manager to notify TEI when we can schedule final.
07/27/22 – IBI PASSES inspection!  Project complete!