PM: Matt Butz, Eryn Thamann
01/29/25 – Met onsite 01/27 to review scope and SOSS requested.
02/25/25 – SOSS provided for Elevar/TEI. Pending approved PO.
03/26/25 – Pending PO approval. Onsite meeting with City AHJ is scheduled for 03/27 to walk spaces and review for any AHJ concerns.
04/24/25 – Elevar had site visit walk-thru AHJ to review life safety concerns. City concerns sent out in meeting minutes with sketches. HCFD needs to confirm additional scope as indicated by AHJ. Elevar will work on stair scope only for now.
05/28/25 – Elevar provided drawing backup to TEI on 05/28. After MEP design is DD level, a design review meeting will be scheduled with HCFD. Elevar to provide design schedule and will need to meet with HCFD to review Div 01 requirements.
06/26/25 – Design review meeting scheduled for 06/30 to review CD set.
07/31/25 – HCFD has 95% set. Waiting on approval prior to preparing final bid set. Elevar to provide clarification on fee per MB’s request.
08/28/25 – Discussing remaining fee with MB/TEI.
09/25/25 – Part of 2026 new project requests.
10/30/25 – Uploaded to Archibus.
12/11/25 – No update.
01/29/26 – Elevar met with HCFD to review 90% set and provided overview sheet for security committee. Waiting on security committee approval before proceeding with CDs. Project needs to be bid/award in 2026.
02/26/26 – Waiting on security committee approval before proceeding with CDs. Elevar has picked up internal revisions and ready when HCFD obtains approval.
03/26/26 – HCFD to setup security committee approval before proceeding with CDs.
04/30/26 – On hold pending HCFD approval of bidding costs.
05/28/26 – Out to bid now with bids due June 30.
06/25/26 – No update.
07/30/26 – Contractor recommendation provided to HCFD and contracts are in process with Purchasing.
08/27/26 – In final stages of contracts with Purchasing.
09/24/26 – Contract was finalized.
10/29/26 – Procurement starting but no submittals yet.