PM: Rycca Thacker, Eryn Thamann
01/29/25 – SOSS requested. JN to confirm what buildings are included in SOSS.
02/25/25 – Pending approved PO.
03/26/25 – First site walk 03/27 at 230. Other buildings shall be scheduled after initial 230 bldg walk.
04/24/25 – 230 Building progressing. Examples with a few questions sent to HCFD for review/approval on 04/22. Elevar is scheduling other buildings with onsite facility managers.
05/28/25 – Example of 230 building was approved by HCFD. Site walks for TPC, 800, CH buildings have also been performed. Need updated drawings for JC care pods and TPC to accurately show floor plans. Need facility manager contacts for remaining locations to schedule site walks.
06/26/25 – JC walk-thru scheduled for 07/02 – 07/03.
07/31/25 – JC walk-thru occurred and Elevar has questions re: JC. Elevar received CH comments from Court Admin and an additional walk-thru is needed to confirm map orientation. Remaining buildings have not been walked yet.
08/28/25 – Evac maps for 230 building provided to HC on 08/27. Other buildings are ongoing.
09/25/25 – All maps will be provided before 11/01. Building 230 has been turned over.
10/30/25 – Evac maps are progressing and on schedule for 11/01 deadline except for a few floor plans where Elevar doesn’t have updated plans and can’t get updated plans.
12/11/25 – All buildings except Hillcrest campus and 6th Floor CH plans have been provided to HCFD with additional JC detainee-area evac plans.
01/29/26 – One floor of CH and Hillcrest to be completed by end of next week. Awaiting Tri-County drawings.
02/26/26 – Elevar working on final 111 Tri-Co drawings now and expect completion in approx. one week.
03/26/26 – Complete with 111 Tri-Co. Portion of Hillcrest remains until further notice.
04/30/26 – Complete. Keep project open for Hillcrest?
05/28/26 – No update.
06/25/26 – No update.
07/30/26 – No update.
08/27/26 – SOSS provided to complete 1701.
09/24/26 – No update on SOSS for 1701. CAD/pdfs provided to HCFD for other completed buildings.
10/29/26 – No update.