PM: Matt Butz, Mike Barth
08/26/21 – HCFD sends TEI signed PO and SOSS. TEI contacts HCFD PM to schedule design kick off meeting. Date pending.
10/26/21 – TEI has begun the design process by setting up the CAD file drawings and using archive data to begin the demolition drawings. Once kick off meeting occurs, the field investigation will be scheduled and the design will proceed.
12/13/21 – TEI has taken the as-build documents to create demolition drawings. Next step is to field verify/document the existing conditions. Field work to be scheduled with building manager. design kick off meeting occurred with HCFD and building manager.
01/25/22 – TEI fieldwork pending return of background checks for James Smiddy and Alex Woods.
02/23/22 – Background checks approved and badges approved. TEI and HCFD to schedule field work with building manager. Note – there was an issues with the existing Simplex FA System panel (dialer power supply) and JCI sent a quote for a complete panel replacement. TEI and JCI investigating a more cost effective fix until a time when the system is replaced.
04/27/22 – TEI hires MobilComm to provide survey of signal strength for FF radios (per CFD requirements). Upon receipt of report from MobilComm, recommendations for BDA may be included in design specifications. TEI fieldwork complete. Existing conditions documented and moving forward with new work drawings.
05/26/22 – MobilComm reports back that the building has a non compliant system. New BDA system will be installed. TEI Meeting with Fire Marshall on 06/07/22 with 90% complete documents for review/input.
06/28/22 – Project deign near complete – Pending Barth review, documents will be sent to HCFD Week of 7/4/22 for review and comments. ITB will be issued upon receipt of review comments.
07/27/22 – TEI sends drawings to Hamilton County facilities for review. Upon receipt of review comments, the package will be issued for bidding.
08/24/22 – Project being sent to purchasing on 08/26/22 for bidding. Available to bidders on 08/30/22. Prebid scheduled for 09/14/22 and bid opening scheduled for 09/28/22. ITB # 075-22.
09/26/22 – Project bidding. Bids Due 9/28/22.
10/26/22 – Bids received and opened. DK apparent low bidder. JCI/Simplex vender in bid. TEI vets bid and makes recommendation for award. Project to commence upon contract approval and PO to DK.
12/15/22 – DK signs and returns contract to HCFD. Once PO is issued, pre-construction meeting to be scheduled.
01/25/23 – DK receives contract and PO. HCFD and TEI working to schedule preconstruction meeting to kick of construction.
02/23/23 – Preconstruction meeting completed. JCI developing submittals.
03/29/23 – TEI speaks with JCI about submittal package. JCI estimates that the submittals for the 800 building will be completed and turned over to DK in the next 2-3 weeks (Mid April-ish).
04/27/23 – TEI follows up with JCI, submittals nearly complete. JCI indicated that the submittal package should be sent to DK on or before 05/01/23. TEI to review upon receipt.
05/23/23 – TEI receives, reviews, and returns submittals with minimal marks, asks for schedule from DK for commencement of work. JC sends photo of material that was shipped to DK for project. TEI to schedule pre-construction meeting first week in June.
06/28/23 – TEI requests schedule again from DK. Upon receipt of schedule, construction to commence pending procurement of materials.
07/26/23 – construction kickoff meeting scheduled for 7/28.
08/24/23 – DK to mobilize to project site and start construction on 9/5/23. Josh Querry from DK to PM/site Super the project.
09/26/23 – Construction has began. DK installing backbone of the system.
10/26/23 – Backbone installation complete. DK has started on upper floors and at the construction meeting on 10/25/23 stated that 18, 17, 16 and part of 15 is complete. DK also working in basement and installing devices there. Rooms are being identified that require either LEADs clearance or special access. DK to schedule work in these areas during day shift.
12/06/23 – Construction progressing. Working on installs in LB, B 1,2,3,3M. LB and B ready for change over. 2 will be by Christmas. 1, 3 and 3M will be nearly complete if not complete by Jan 1.
01/30/24 – DK submits CO request for portion of work changes. The beam detector CO still pending.
02/28/24 – Beam detector CO still pending.
03/27/24 – Beam detector for 3 beam detectors received ($41k). HCFD to determine if it is accepted or not. Smoke purge CO under review.
04/24/24 – Smoke purge CO verbally approved to DK at const meeting. Beam detector CO not approved at the meeting. Work continues through the building.
05/29/24 – The smoke purge CO has been approved and sent to DK. DK and JCI working on Drawing updates and will progress to install as soon as the revised install drawings from JCI complete. JCI indicated that all parts are readily available.
06/26/24 – No updates from JCI on this project.
07/24/24 – DK same staffing issues – staff being moved from 800 to JC and back. CO verbally approved (HCFD waiting on PO increase) for formal approval.
08/28/24 – JCI submits revised drawings wot city for approval. JCI states that there is no way (on existing system) to repair the amplifier card for the upper floors. TEI and HCFD directed JCI that the New system shall be turned on immediately and use the new devices for audio on the upper floors.
09/25/24 – TEI, DK and HCFD meet with inspector (Jeff Hinkel) to discuss inspection process and 3 and 3M. Inspections will proceed similar to CH and TPC, where we will have multiple teams and multiple inspections. Looking at options for the 3 and 3M area – inspector sympathized with the task and we developed possible workable solutions.
10/30/24 – The switchover of floors to the new system in the tower (top down) has commenced. Anticipate tower work to be completed in approx 2-3 weeks. then move to low rise floors. TEI recommends scheduling inspection of tower floors once tower complete.
12/11/24 – HCFD, CFD, CBD, JCI, DK and TEI participate in the first acceptance inspection at the building. Floors 7-18 were inspected and accepted, with minor tweaks. Construction continues, with the crews starting on 5th floor week of 12/16.
01/29/25 – Crews working on 2 right now. Next inspection scheduled for 02/12/25 at 5:00 PM. Planning for inspections of floors 2-6.
02/26/25 – Inspections for 2-6 went well. First floor complete and working in basement. Will be ready for next inspection in about a month. Then there will be the Flow/Tamper inspections, then AHU/smoke control inspections, then Elevators. Need resolution of elevator issues for the non-functioning elevators.
03/26/25 – Inspection for SB, B and 1 scheduled for 04/16/25. The tamper/flow inspection to be scheduled 2-3 weeks after the inspection on the 16th.
04/23/25 – All floors inspected for smokes, pulls, heats and AVs. Door holders were inspected. Tamper/flows inspection next – to be scheduled TBD.
05/28/25 – Tamper flow inspection occured and passed. Next is air handlers. Inspector allows the magna-helic results from the pre-test to be written on the covers for the inspection night.
06/25/25 – Installation nearing completion. Elevtor and Air Handler inspections scheduled for 07/16/2025
07/30/25 – Freight elevator and final air handler inspections scheduled for 07/31/25 at 0700. This is final building and fire and elevator inspections pending no issues during the inspections.
07/31/25 – Early morning inspection went well this morning. Three small electrical items are required to be updated to get the AHU-45 and Smoke Fans 14 & 15 did not start. The elevators are approved and the Chief Inspector approved the current smoke detector layout.
08/27/25 – follow up visits with CFD and CBD to inspect and approve the repairs made by HC. All inspections completed (other than IBI). IBI to be scheduled once the Bldg Dept and FD upload all their paperwork.
09/24/25 – All inspections passed. HCFD and DEG to schedule final punchlist for project.
10/29/25 – Punchlist completed and issued punchlist to DK.
12/10/25 – project tied to Justice Center PO. Closeout pending completion of JC FA project.
01/28/26 – Project tied to the JC FA PO, Closeout pending completion of JC FA project. Anticipated completion April/May of 2026.
02/25/26 – No Updates.
03/25/26 – No Updates.
04/29/26 – No Updates.
06/23/26 – DEG directs DK to assemble and submit closeout documents for 800 building.
07/29/26 – Project completion pending closeout documents.
08/26/26 – Project complete pending closeout documents.
09/23/26 – Project complete pending closeout documents.
10/28/26 – Project complete pending closeout documents.