PM – Rycca Thacker, Mike Barth
08/26/21 – HCFD sends signed PO and SOSS to TEI. TEI to start immediately, as the switchgear cleaning work is contingent on the this work.
10/26/21 – TEI submits preliminary plans and opinion of probable cost to HamCo for review. Project pending project funding.
12/13/21 – TEI and HCFD gets quotation from CE Power to provide the install of the work. HCFD drafts and issues a PO for the work to be installed, and requests schedule from CE Power.
02/23/22 – All equipment has been ordered and anticipated delivery was end of February, early March. CE Power to notify TEI and HCFD upon receipt of all equipment and schedule installation and cleaning.
04/27/22 – Equipment is installed in the building. HCFD and TEI requesting dates from CE Power to perform Switchgear PM and Tie ins during same outage. Tie in pending CE Power availability.
05/26/22 – Tie in date tentatively scheduled for June 20 (Juneteenth Holiday). Pending approval from HCFD and JFS personnel. JFS requested that it move to as Saturday in case there were issues and needed the Sunday for repairs. Final date TBD.
06/28/22 – Date of tie in moved to 07/09/22. Tie in to be competed concurrently with switchgear cleaning (same power outage).
07/27/22 – Power outage cancelled by Duke energy due to tornados in the area, and unavailability of Duke crews. CE Power, HCFD, JFS and Duke to reschedule.
08/24/22 – Reschedule date is 09/10/22 pending no storms etc. in area.
09/26/22 – Installation complete. testing, training and punchlist to be scheduled.
09/29/22 – Work on SOSS for putting CRAC and Condenser on backup power.
10/26/22 – TEI submits SOSS for placing CRAC unit condensers on the backup power. project pending SOSS approval.
12/15/22 – TEI receives approved SOSS and PO. Project Design in progress.
01/25/23 – CE power punchlist incomplete. TEI sends follow up email to request that the work completed ASAP. Alex on site on 01/25/23 to confirm the existing power feeds to the condensing units, and a review set will be send to HCFD prior to bidding.
02/23/23 – TEI to submit to HCFD bid set for final review.
03/29/23 – TEI to submit review set to HCFD by 05/03/23.
05/23/23 – TEI submits review set to HCFD for comments. Upon receipt of owner review comments, project will be issued for bids (small projects method).
06/28/23 – TEI, RT and Kleeman meet on site and discuss project. Trades electricians to provide installation of the circuits. TEI to procure the permit from IBI for trades.
08/24/23 – Drawings are submitted to IBI for permit. Comments received and answered from IBI. Permit expected in next day or two.
09/26/23 – Plan review complete and permits ready to be picked up at IBI. TEI will deliver to HCFD for work to be completed by trades.
10/26/23 – TEI procures the permit for the work and sends to HCFD. Trades to install work.
12/06/23 – Trades to notify TEI when they are ready for inspections.
01/30/24 – Trades completes work. TEI and Trades have IBI inspect work and passed inspections on 1/30/24.
02/29/24 – Project complete, need as-builts to close out.