Hamilton County Facilities

JC – Fire Alarm System Upgrades

PM: Matt Butz, Mike Barth
08/26/21 – HCFD send signed PO and SOSS to TEI. TEI contacts HCFD PM to set up design kick off meeting, date is pending.
10/26/21 – TEI has began the design process, setting up drawings and using archive drawings to show on demolition plans. Once kickoff meeting occurs, the field verification process will occur and the project will proceed.
12/13/21 – TEI develops demolition drawings from existing building plans from archives, and conducts design kick-off meeting with HCFD and building manager.  Next step is to schedule field work to document/confirm existing conditions.  TEI to work with building manager on schedule.
01/25/22 – TEI fieldwork pending return of background checks for James Smiddy and Alex Woods.
02/23/22 – Background checks returned and employees badges approved.  TEI and HCFD to schedule the field work with building managers.
04/27/22 – TEI hires MobilComm to provide survey of signal strength for FF radios (per CFD requirements).   Upon receipt of report from MobilComm, recommendations for BDA may be included in design specifications.  TEI fieldwork complete.   Existing conditions  documented and moving forward with new work drawings.
05/26/22 – MobilComm reports back that the building has a non compliant system.  New BDA system will be installed.  TEI Meeting with Fire Marshall on 06/07/22 with 90% complete documents for review/input.
06/28/22 – Project deign near complete – Pending Barth review, documents will be sent to HCFD Week of 07/04/22 for review and comments.   ITB will be issued upon receipt of review comments.
07/27/22 – TEI sends drawings to Hamilton County facilities for review.  Upon receipt of review comments, the package will be issued for bidding.
08/24/22 – Project being sent to purchasing on 08/26/22 for bidding.  Available to bidders on 08/30/22.  Prebid scheduled for 09/14/22 and bid opening scheduled for 09/28/22.  ITB # 075-22.
09/26/22 – Project out for bids.  Bids open 09/28/22.
10/26/22 – Bids received and opened.  DK apparent low bidder.  JCI/Simplex vender in bid.  TEI vets bid and makes recommendation for award.   Project to commence upon contract approval and PO to DK.
12/15/22 – DK signs and returns contract to HCFD.  Once PO is issued, pre-construction meeting to be scheduled.
01/25/23 – DK receives approved contract and PO.  HCFD and TEI working to schedule preconstruction meeting to kick off the construction.
02/23/23 – Pre construction meeting completed.  JCI developing submittal documents.
03/29/23 – TEI speaks with JCI about status of Submittal Package.  JCI states that the submittals are tracking about 2-3 weeks behind the 800 Broadway submittals (anticipated receipt of submittals = late April to Mid-May).
04/27/23 – JCI indicates that the submittals for the JC shall be sent to DK by mid May.  Still tracking same as indicated last month.  TEI to review and turn around upon receipt of submittals.
05/23/23 – JCI indicated that the submittals will be sent to DK this week.   DK has not received to date.
06/28/23 – DK has not sent submittals to TEI for review to date.  Submittals will be reviewed by TEI upon receipt.
07/26/23 – TEI receives submittals for project.   Reviewing and will return.  Pre construction meeting (along with 800) is scheduled for 7/28.
08/24/23 – TEI, HCFD and DK meet (at 800) to discuss project.  work in JC to mobilize late Q1/early Q2 of 2024.  Matt Butz asks about the BDA equipment at the JC, and how quickly it can be installed (issues with the existing system).  TEI reaches out to DK to request data about schedule.
09/26/23 – TEI reaches out to DK for CO cost to install the ERRS (BDA) ASAP versus waiting until the new JCI system is in the building.  MobilCOMM states no issues with the plan.   DK sending electrician to site to confirm existing system is compatible and will issue CO accordingly.  TEI stresses with Gleason that time is of the essence.
10/26/23 – MobilCOMM has ordered to BDA for the JC and will schedule the installation upon receipt of the equipment.  DK still on schedule to mobilize as previously identified.
12/06/23 – TEI asks DK to find status of BDA – should be at MobilCom per previous schedule.  TEI will follow up with DK.
01/30/24 – Installation of BDA pending the background checks from MobileComm
02/28/24 – MobileCOMM cleared to work in building.  TEI contacts DK and tells them that the install must be scheduled and we need to have install date by beginning of February partner meeting.
03/27/24 – MobilComm and DK to mobilize 4/1/24 to install and get the BDA installed ASAP.
04/24/24 – Work has began on the BDA upgrades,  most work in basement complete and 1st floor is next.   All areas with minimal/no coverage were addressed first.
05/29/24 – BDA installed and turned on in the lower levels of both buildings.   Finalizing the install of the BDA in the next week or two.  Started the install of the backbone for the JCI fire alarm system.
06/26/24 – BDA installed and complete. DK and Biederman working out PO issues to get permitted. Panels installed and backbone conduits being routed through the building. DK facing additional staffing issues.
07/24/24 – Staffing issues continue. Permits for BDA applied for – pending City approval. Work continues on backbone. DK developing means and methods and durations of timing needed in all inmate areas to coordinate with HCSO. JCI finalizing CO pricing for deluge system, but Jay at JCI tells TEI that the relays needed for the CO are currently on backorder and the scheduled ship date is 01/31/2038 (and this is NOT a typo!). TEI states this is NOT acceptable!
08/28/24 – Project in construction. Permits for BDA obtained, inspections completed (passed) and MobilComm to send approval paperwork to HamCo once received.
09/25/24 – Construction progressing in the building.
10/30/24 – Construction progressing in the building following behind the cell lock project.
12/11/24 – DK indicates that the backbone installation is nearly complete and that they will need to have JCI and Notifier at the next const meeting (01/08/25) for coordination of cross trip.
01/29/25 – Cross trip installed and working. DK to have JCI at next project meeting to review schedule and Deluge system (controlled on all floors).
02/26/25 – JCI, HCFD, and TEI meet to discuss deluge system on site. TEI sent JCI record dwgs of sprinkler system in building. Construction on-going.
03/26/25 – JCI has all parts for Deluge upgrade to DK. The Deluge upgrade to begin early April.
04/23/25 – Deluge work has started. Working in unit 1 of north tower, all floors. Then Unit 2 North, and so on.
05/28/25 – Side 2 of the north building to be completed in the next 2 weeks.
06/25/25 – Issues with the Deluge valves and water leaks. TTC attends FA meeting and evaluates the valves and to send in recommendations.
07/30/25 – Construction on the project progressing with availability of spaces. DEG submits memo with recommendations.
07/31/25 – TTC issued memo on the deluge valve issue in the North building. We will talk more about this after the meeting today.
08/27/25 – Construction progressing. Moving to south tower beginning of September.
09/24/25 – Construction progress continues. DK following the other projects as pods are made available.
10/29/25 – Construction progress ongoing. Anticipated completion April/May of 2026
12/10/25 – Construction progress ongoing. Change order issued at the OEC meeting today. JCI finalizing engineering change for the building department.
01/28/26 – All work (original Scope) in North tower near complete. JCI to submit documents to city by end of Janaury. Project ongoing. Anticipated completion Late April/Early May 2026.
02/25/26 – Project ongoing. Deluge work is being completed this week and next.
03/25/26 – Project ongoing.
04/29/26 – Pretest completed on 04/28 throughout both buildings. Consult with inspector to be scheduled to outline inspection process.
07/29/26 – 2 months of inspections completed and the CFD and CBD have approved all of the installations. DEG has assembled the punchlist for the project and issued to the EC. Most items were discussed at time of inspection and punchlist walk – and we anticipate that they have been completed. Training for building staff was 07/28/26.
07/30/26 – Electric issues at panel and distribution at fire pit shorted out. Wire ran in lighting conduit and DK has to do an emergency repair for the job. MB to investigate and report back.
08/26/26 – Project complete pending final IBI and Elevator inspections for JCI to sign off on permit. Scheduled for Week of 08/31. Closeouts requested from DK.
09/23/26 – All inspections except IBI complete. IBI pending renewal paperwork. Project pending final closeout.
10/28/26 – IBI final inspection passed and complete. Project pending closeout documents.