Hamilton County Facilities

800 – Fire Pump Replacement

PM: Matt, Terry Cannon
Engineers: Coty Groeschen, Wesley O’Hara
08/27/25 – Prebid held today, bids are due in September. Owner furnished equipment includes fire pump, jockey pump, low suction controller and fire pump controller.
08/28/25 – Issued for Bid 8/13 and bids open 9/24.
09/24/25 – Bid Opening today at 11AM.
10/03/25 – Post bid meeting held with Alpha and they are recommended for the project. Base bid no alternates accepted.
12/12/25 – Jesse reported contracts close to being sent to contractor for signature.
01/25/26 – Contract should have went to BOCC on Jan 19, no updates. Sending Permit Drawings Tuesday 2/3. Electrical RFI received and in the process of being answered.
02/12/26 – DEG starting pre-construction work with Alpha and subs.
02/25/26 – Contracts are back. DEG coordinating with Duke and IBI on power installation requirements for the MI cable. Alpha EC vendor being weird about MI cable requirements and cost.
03/25/26 – Alpha arranging EC vendor for this job. DEG working on necessary CFD details before work begins.
04/22/26 – FDC testing complete and 800 passes inspection. DEG checking with Alpha on starting this project and getting permits to begin. A project schedule should be ready to share with the owner in a couple of weeks.
05/27/26 – SOV was approved today. We are ready to set up the Pre-Const meeting. DEG sent mechanical drawings for permitting to Alpha last week adn IBI drawings are already in for permitting.
06/25/26 – Kickoff meeting held with contractors. IBI permit approved, City permit under review. Electric change order under review. Schedule, SOV, Site safety documents received and under review.
07/30/26 – Had meeting with vendors on electric change order. Third meeting scheduled today at 1PM. Prices are coming down but not going away. Met with CFD and received their thoughts on allowing the high rise fire pump to provide temporary service for both low and hi rise, they are amendable provided we provide a letter stating it will work. Griffith sent us that letter.
08/26/26 – CO-1 sent and signed by DEG and Alpha, returned to County for approval. Planning on scheduled work to begin in October after Duke power is stable.
09/23/26 – 9/26 shutdown pushed back to Veterans Day. Alpha agreed to January 2027 startup without the project incurring any additional cost.
10/26/26 – JTL requested site visit to start working on the electrical portion of the job. DEG informed them to coordinate with Facilities on access adn that we wanted to be cc’ed on all visits so we can stop in and check progress.