PM: Rycca Thacker, John Millar
08/28/25 – County asked THP to review water infiltration at the coroner building.
09/05/25 – THP completed an initial site visit to investigate the conditions.
02/25/26 – THP had follow meetings and discussion with HC. THP published an email with summary of potential leak areas and an opinion /of probable costs.
04/03/26 – Based on THP recommendations, County directed THP to complete water tests of the suspect areas.
04/09/26 – THP and HC staff completed water testing at the louvers and screen wall. Testing found multiple leaks in the screen wall.
06/25/26 – Project Archived.