800 – Low Rise AHU Replacements

PM: Matt Butz, Terry Cannon
01/17/25 – SOSS requested.
02/26/25 – TTC still needs to submit this SOSS, this is the last one on my list to submit.
03/25/25 – Internal kickoff meeting held this month. Drawings are being updated with existing conditions for the building. Our first design meeting to be in April.
04/23/25 – Project underway. We have completed our first field trip to the building. TEI running load calculations to verify sizing, setting up existing drawings and working on ventilation calculations. After we get the preliminary design complete, let’s meet and discuss project particulars.
05/28/25 – We held a kickoff meeting with the Facilities in the last month and made another round of field trips to the building for additional information. We are trying to prove HVAC AHU sizing from original job and collect factory information from original install of the low rise units to verify coil sizing, heating and cooling loads and whether or not air side economizers make economic sense during this replacement.
06/25/25 – ThermalTech doing additional fieldwork to lock down actual ductwork in the mechanical rooms. We should be ready for bidding next month.
07/31/25 – Project submitted for Owner Review. Project Manual didn’t make it through TTC review, will be sent later. Look for prebid third week of August.
08/26/25 – Prebid meeting Wednesday 8/27. TTE invited many.
09/24/25 – Addendum 1 previously released. Bid opening today at 11AM.
10/29/25 – Project on hold pending official bid award. TTC answered Nester email inquiry this morning about award status. TEI/DEG has not advised either bidder the project has been awarded yet.
12/12/25 – in contract approval stage. TTC notified contractors that Triton received the bid and Alpha did not.
01/25/26 – Sent before BOCC on Jan 19 for approval. We are awaiting notice to proceed.
02/12/26 – Contracts are back. Pre-Const meeting being set up now.
02/25/26 – Triton has been awarded the project. We are scheduling the project kickoff meeting soon. We do need to discuss what are we going to do with AH-71 and it’s proximity to the parapet wall.
03/25/26 – Submittals coming in, no kickoff meeting scheduled yet.
04/26/26 – DEG working on change order request drawing to relocate AHU-L71 to farther away from parapet wall. Once complete we will get a price from Triton for the change.
05/27/26 – DEG sent revised AHU-L71 location to Triton for pricing to rotate away from parapet to get 10 foot clearance.
06/25/26 – Awaiting project kickoff. AHU-71 change order not received yet.
07/30/26 – Pre Construction meeting held with Triton. Working on submittals, sent permit drawings to Triton, working on getting project n place for January start so unit can be replaced over long County weekend.
08/26/26 – Reviewing submittals preparing for January start.
09/23/26 – Still on track for January start, no new submittals in September from Triton.
10/26/26 – Had meeting with Triton and Emcor on HVAC Controls. We are awaiting the resubmittal of the controls package to DEG for full review. The controls have not been approved for this project yet. AHU submittals including curbs are approved. We are verifying current lead time for equipment.