Hamilton County Facilities

800 – 6th Floor Reno & Bsmt Plumbing Repairs

PMs: Sarah, Terry Cannon, Eryn Thamann
01/17/25 – SOSS Requested.
02/25/25 – SOSS submitted to HCFD. Pending approved PO.
02/26/25 – Awaiting approved SOSS.
03/25/25 – Internal kickoff meeting held this month. Drawings are being updated with existing conditions for the building. We will follow Elevar lead on first design meeting. TEI scope is in the basement and the 6th floor area. Elevar hasn’t received approved PO.
04/24/25 – PO provided and awaiting design kick-off meeting with Court Admin/team.
04/23/25 – Project setup and internal meetings underway. Elevar and ThermalTech setting up kickoff meeting.
05/28/25 – Awaiting kickoff meeting with Elevar and County. TTE ready to mobilize for design.
06/25/25 – Kickoff meeting in July.
07/30/25 – Drawings received from Elevar, ThermalTech working on MEP design, submitted questions about need for MSB in new restroom. Additional fieldwork done last week for basement repairs.
07/31/25 – Drawings are progressing for a bid review set Aug 8 and a bid set to HC Purchasing Aug 15. TTC changed name and assigned to Elevar and merged Plumbing Repairs and 6th Floor Reno.
08/28/25 – Project scheduled for bid advertisement on 08/29.
09/25/25 – Bids due 10/10. Last addendum due out 09/26 with final questions.
10/30/25 – Lowest bid was Triton and under advertised cost. Vetting mtg occurred and Elevar has recommended Triton for award.
12/11/25 – Project awaiting final contract award from purchasing.
01/29/26 – No update.
02/26/26 – Contract was approved but Elevar has seen no submittals or correspondence. Elevar to schedule construction kick-off mtg.
03/26/26 – Contract was approved but Elevar has seen no submittals or correspondence.
04/30/26 – Have reviewed some general trade submittals.
05/28/26 – Possibly complete with submittals but low on Triton’s priority list.
06/25/26 – No update as it’s low on Triton’s priority list. Not received change order pricing for flooring add.
07/30/26 – Construction kickoff meeting held 07/20. Recurring progress meetings scheduled.
08/27/26 – Triton likely back onsite now after ACM removal. Regular progress meetings to resume next Mon. We will keep the floor drain in the project based on today’s conversation.
09/24/26 – Working thru slab change order.
10/29/26 – New pricing is expected soon for slab work.