PM – Rycca Thacker, Mike Barth
10/26/21 – ThermalTech receives signed SOSS and PO. HCFD asking for design to be complete by 11/05/21.
12/13/21 – TEI submits drawings to TEI with to HCFD for review. RT returns drawings to TEI with additional scope changes. TEI to finalize drawings for issuance by EOY.
01/25/22 – TEI sends drawings to HCFD for review and final comments, to be issued upon receipt of comments.
02/23/22 – TEI sends drawings to Glenwood Electric to obtain quote (since Glenwood is under warranty for system). Upon receipt of quote from Glenwood, TEI and HCFD will determine next steps.
04/27/22 – TEI reviews quote with RT and Glenwood. Recommendations forwarded to JFS. Next steps pending approval from JFS.
05/26/22 – JFS approves the Glenwood quotation. HCFD executes CO for project and Glenwood is procuring materials. Install to occur upon receipt of materials.
06/28/22 – Install to occur pending material procurement.
07/27/22 – Install to occur pending material procurement.
08/24/22 – Install to occur pending material procurement. As of 8:00 PM on 8/24/22, Glenwood received materials at their shop on 08/24/22. Glenwood is coordinating resources and will contact Rycca Thacker in the next few days to schedule installation.
09/26/22 – Project in construction phase. Upon notification from Glenwood that install is complete, TEI and HCFD will perform punchlist.
10/26/22 – TEI and HCFD to perform punchlist.
12/15/22 – TEI and HCFD to perform punchlist.
01/25/23 – There were hardware issues on the stair tower doors. Glenwood ordered replacement hardware and tentative ship date is approx 3 weeks. TEI will finalize punchlist upon installation of pending hardware.
02/23/23 – Project completion pending installation of hardware.
04/27/23 – Project completed. RT and TEI perform punchlist walk through. Upon receipt of all close out materials, can be archived.
05/23/23 -Waiting on receipt of all close out materials.