Hamilton County Facilities

A&D – 7th Floor Access Control Modifications

PM – Rycca Thacker, Mike Barth

10/26/21 – ThermalTech receives signed SOSS and PO. HCFD asking for design to be complete by 11/05/21.

12/13/21 – TEI submits drawings to TEI with to HCFD for review.   RT returns drawings to TEI with additional scope changes.  TEI to finalize drawings for issuance by EOY.

01/25/22 – TEI sends drawings to HCFD for review and final comments, to be issued upon receipt of comments.

02/23/22 – TEI sends drawings to Glenwood Electric to obtain quote (since Glenwood is under warranty for system).  Upon receipt of quote from Glenwood, TEI and HCFD will determine next steps.

04/27/22 – TEI reviews quote with RT and Glenwood.  Recommendations forwarded to JFS.  Next steps pending approval from JFS.

05/26/22 – JFS approves the Glenwood quotation.   HCFD executes CO for project and Glenwood is procuring materials.   Install to occur upon receipt of materials.

06/28/22 – Install to occur pending material procurement.

07/27/22 – Install to occur pending material procurement.

08/24/22 – Install to occur pending material procurement.  As of 8:00 PM on 8/24/22, Glenwood received materials at their shop on 08/24/22.   Glenwood is coordinating resources and will contact Rycca Thacker in the next few days to schedule installation.

09/26/22 – Project in construction phase.  Upon notification from Glenwood that install is complete, TEI and HCFD will perform punchlist.

10/26/22 – TEI and HCFD to perform punchlist.

12/15/22 – TEI and HCFD to perform punchlist.

01/25/23 – There were hardware issues on the stair tower doors.   Glenwood ordered replacement hardware and tentative ship date is approx 3 weeks.  TEI will finalize punchlist upon installation of pending hardware.

02/23/23 – Project completion pending installation of hardware.

04/27/23 – Project completed.  RT and TEI perform punchlist walk through.  Upon receipt of all close out materials, can be archived.

05/23/23 -Waiting on  receipt of all close out materials.