Hamilton County Facilities

EV Charging Stations RFP

PM John Nester, Mike Barth

10/26/21 – ThermalTech receives signed SOSS and PO for project. RFP in development.
13/13/21 – HamCo advises TEI to hold on the RFP development until a time when the county develops policy on the use/locations etc. of the EV Charging stations.   TEI on hold until directed otherwise from county.
01/25/22 – TEI receives notice from JN that the project will move forward as originally discussed.  TEI and JN to schedule kick off meeting the beginning of February
02/23/22 –  TEI submits list of questions for RFQ to HCFD.   Kick off meeting with HCES scheduled for 03/01/22 at 3:00 PM.  Upon receipt of direction from the HCES, RFQ will be finalized.
04/27/22 – HCFD determines that the Infrastructure needs to be bid separately from the service contract.  TEI develops infrastructure plan (SD level), includes power for the mobile coach, and has review meeting with HCES, HCPH, and HCFD on 04/26/22.  CD phase and implementation pending funding approval from County.
05/26/22 – TEI finalizes the SD package after review with the end users (drawings and revised opinion of probable cost).  TEI submits SOSS for CD thru CA phase of the work.  Work pending SOSS approval and PO.
06/28/22 – Work pending SOSS approval and PO.
07/27/22 – Work pending SOSS approval and PO.
08/24/22 – TEI receives Signed SOSS and PO.   JN states that funding for the install will be in 2023, and to work towards a first of 2023 issuance date for the project.
09/26/22 – TEI working towards an issuance at the end of the year for the infrastructure ITB for now. We can draft the RFP now but it has to be open for future stations.
10/26/22 – TEI working towards an issuance at the end of the year for the infrastructure ITB for now. We can draft the RFP now but it has to be open for future stations.
12/15/22 – Project documents in QC phase at TEI.  Will be sent to HCFD once QC review complete for review and then issued for bidding.
01/25/23 – TEI to send final review set to HCFD for review by 02/10/23.  Project bidding pending HC policy and procedures implementation decisions.
02/23/23 – Project bidding pending HC Policy and procedures implementation decisions.
03/29/23 – Project bidding pending HC Policy and procedures implementation decisions.
04/27/23 – Project bidding pending HC Policy and procedures implementation decisions.
06/28/23 – HC policy has been worked on by ES.   Location for the EV charging stations has been moved from 250 WHT to Civic Center  Drive (Comm  Center), and also to include the Regional Crime Lab in Blue Ash (common provider).  TEI and JN to discuss modifications to existing SOSS.
08/24/23 – TEI visits the site with the building manager and determines path/routing of power feeds for the EV charging equipment.  Discusses with JN, and will modify new SOSS for new location.
09/26/23 – TEI develops plan for drawings and sends to HCFD for review/approval.
10/26/23 – TEI has Underground detective locate existing utilities on site,  TEI shows on plan and HCFD submits to ODOT for approval.
12/06/23 – TEI submits documents to HCFD to submit to ODOT for approval.  Pending ODOT approval.
03/27/24 – Tracking this on other project.