PM = Rycca Thacker, Mike Barth
12/13/21 – JFS issues RFQ and bids come in significantly higher than expected. TEI and HCFD to develop an ITB with a clearly defined scope for rebidding purposes.
01/25/22 – TEI working on RFQ – will submit to RT for review and comment.
02/23/22 – TEI and Rycca to finalize requirements of scope and develop bidding schedule for the ITB.
04/27/22 – TEI and Rycca to finalize requirements of scope and develop bidding schedule for the ITB.
05/26/22 – TEI and Rycca discuss scope items and TEI is finalizing the ITB for HCFD review and approval. TEI to submit to HCFD by June 10.
06/28/22 – TEI submits the final draft of RFP to HCFD for review. Issuance of ITB pending review comments and direction from HCFD.
07/27/22 – The project is currently in the bidding phase. Bids are due 8/26/22. Prebid meeting scheduled on 08/03/22.
08/24/22 – Prebid meeting conducted and addenda issued. Bids are due Friday 08/26/22.
09/26/22 – Bids received. Glenwood apparent low bid. TEI vets bid. Recommends Glenwood for the project. In contract phase.
09/29/22 – Archive next month.