PM: Rycca Thacker, Terry Cannon
10/20/21 – SOSS approved.
10/21/21 – Draft project manual distributed for review.
10/28/21 – Project prebid tomorrow 10/29. 12 sites. One base bid Blue Ash, 11 alternates.
11/08/21 – Bid received by TEI. JCI and DK bid the work and Trane declined to submit a bid. Bids were tabulated and sent to County for award.
12/13/21 – This month we worked on getting the contract in place with Debra Kuempel for the Bid Bid and seven Alternates. We continue to work on paperwork and contract. Terry talked to Kerry last Friday about the intent of the specifications and verified with DK that the bids include all the labor and materials for the work. Kerry preparing to write a non-AIA contract for use on this project and warned that an STD contract ADA contract protects the county less than a full ADA contract.
01/25/22 – Contract in signing stages at DK
02/24/22 – Still in contract stages, goes to BOCC this Wednesday and PO after that.
03/31/22 – PreConst next week.
04/28/22 – Pre-const meeting was held. Debra is preparing to start the work and call Scott. Submittals have been sent in for the Marvair unit, DK working on the Indian Hill split system.
05/25/22 – DK is scheduling kickoff meeting and fieldwork with Comm Center. I check in a couple of times with Dave. We also reached out to Mobilcom on alarm monitoring and set up a field meeting with DK and Comm Center to all visit a site to see how the alarms are connected to the AC units so we order them correctly. Submittals are still in my inbox pending this field finding.
06/30/22 – All submittals returned and approved. Equipment is on order DK starting at Indian Hill, however the installed equipment is different than planned, DK taking care of it. Payapps should start this month.
07/27/22 – DK started the Indian Hill site this month and is trying to get three Marvair units for the other sites this summer.
08/24/22 – Indian Hill #1 is complete, #2 is being done this week. Payapp #1 submitted with corrections for payment.
09/25/22 – Payapp #1 submitted, Rycca working with DK on some PW issues. No update on the Marvair units for delivery date, checked in with Dave 2 or 3 times.
10/26/22 – Equipment scheduled to arrive Nov 16.
12/15/22 – About 6 sites are complete and Debra is working on the additional sites daily. They hope to be done by the end of the year if the weather holds up.
01/24/23 – All sites are done and DK has billed for all the material. Scott says as soon as he gets time, he will coordinate a punchlist visit for us.
02/17/23 – Scott, Rycca, Terry performed an punchlist at three sites. TTC to prepare punchlist for DK to use on this project. TTC spoke to Dave about some issues we found in the first few locations and DK will take care of them.
03/29/23 – Closeout documents are under review for this project. Final payapps have also arrived. TTE making three binders for closeout.
04/25/23 – Punchlist sent to DK, O&M printed and will be delivered this week to Rycca. DK to check Eden Park for status.
05/21/23 – Working on closeout and punchlist with DK. Eden Park site was checked for issues.
06/28/23 – Punchlist complete, DK working on closeout documents.
07/26/23 – Signed punchlist sent to County for approval. Final payapps sent in for processing. Ready to archive.