PM: Rycca Thacker, Mike Barth
03/29/23 – TEI submits SOSS for project. Project pending Approval and PO.
03/30/23 – SOSS and PO approved, RT will send.
04/27/23 – TEI starting field work and will develop SD/Cost estimates.
05/23/23 – TEI meeting building manager and HCFD to provide field investigation. TEI evaluates (2) options – direct MCC replacement and replacing with PDP since the motors are served with VFDs now. TEI submits SD PDFs and costs for the work. HCFD to provide next steps.
09/26/23 – TEI submits design drawings to HCFD for review. TEI receives review comments. Drawings finalized.
10/26/23 – Upon determination of XBE requirements, this project will be issued as a small projects bid.
12/06/23 – Project issued for small projects bid. Prebid conducted and Addendum published. Bids due to TEI on Friday 12/08/23 at 4:00 PM.
01/30/24 – Project bids received and vetted. Project in contract approval phase. lead time for equipment will be roughly 12 weeks.
02/28/24 – Glenwood electric is sent the PO and signed contract. Submittals yet to be received/approved by TEI.
03/27/24 – TEI receives submittals and approves. Equipment is being procured.
04/24/24 – Construction kickoff scheduled for 4/29.
05/29/24 – Construction kickoff meeting occurred. Glenwood orders electrical equipment (Scheduled ship date = 11/20/24)
06/26/24 – No Updates.
07/24/24 – No Updates.
08/28/24 – No Updates.
12/11/24 – HCFD, TEI and Glenwood meet on site for Pre-construction meeting. Panel in Glenwood shop – Enclosure no with Panel. Glenwood looking at early January for installation.
01/29/25 – HCFD requests installation schedule form Glenwood.
02/26/25 – Installation to begin in next week or so.
04/23/25 – Project installed, complete and punchlist completed. Pending punchlist and closeout.
05/28/25 – Pending closeout documents.
06/25/25 – TEI approves closeout documents. Project completion pending delivery of binders.
07/30/25 – TEI reaches out to Glenwood for binders.
07/31/25 – OK to Archive, all done.