PM: John Nester, Mike Barth
03/29/23 – TEI Submits SOSS. Project pending approval of SOSS and PO.
04/27/23 – TEI receives PO and Signed SOSS. TEI finalizing drawings for HCFD review and then will get permits for installation by trades.
05/23/23 – TEI sends review set to HCFD. Will apply for IBI permit upon receipt/implementation of owner’s review comments.
06/28/23 – TEI meets with John Nester, Andrea Hatton, In Zelner and the HC Electricians to review. Minor changes were made and the drawings were submitted to Blue Ash for plan review and permit. Plan review passed and permit is ready for pick up at Blue Ash with a balance of $50 +change. TEI to pick up permit for HC and work can commence.
7/26/23 – TEI picks up permit and delivers to trades. Trades is working on the modifications to the branch circuits.
08/24/23 – Trades to notify TEI when work is completed and TEI will arrange for inspections.
09/26/23 – County electricians reach out to TEI for review of as-built documents. Tentative meeting the week of 10/02.
10/26/23 – TEI and county electricians meet to review as-built documents. TEI incorporates the as-builts onto the CAD files. TEI drawings will be sent to HCFD upon completion of QC review.
12/06/23 – HamCo electricians indicate that there are a few more changes that the facility is wanting to make. Electricians to get modifications to TEI to incorporate in the AS-builts.
01/30/24 -The Sally Port Doors were moved to EM power. Electricians Told TEI circuitry information to include on as-builts.
02/28/24 – TEI updating permit drawings and will submit to Blue Ash for engineering review and final final inspections.
07/24/24 – REFERENCE OTHER STRING FOR UPDATES.