Hamilton County Facilities

A&D – First Floor EMF Study

PM – Rycca Thacker, Mike Barth

03/24/21 – HCFD requests SOSS from TEI for an Electromagnetic Investigation of the first floor of the A&D building. ThermalTech soliciting venders to provide us a quote to measure the EM waves in the area, and will submit SOSS once we receive the quotation.
04/28/21 – TEI submits SOSS to HCFD. Project pending approval of SOSS and PO.
05/26/21 – TEI receives signed SOSS and PO. Study phase started.
06/23/21 – TEI, Rycca, Steve T, and Claude T perform walk through of space on 06/23/21 to document the EMF readings in the area of concern. Initial readings were higher than expected levels. Report and recommendations to follow.
07/28/21 – TEI working on report – with continued research for appropriate recommendations.
08/26/21 – TEI nearing wrapping up draft of report to deliver to HCFD. Will complete the report upon completion of 2022 estimates.
10/26/21 – TEI to deliver draft of report to HCFD 11/05/21.
12/13/21 – TEI submitted hard copy draft of report to HCFD for review and comments.  Final report pending HCFD review.
01/25/22 – Final report pending HCFD review.
02/23/22 – Final report pending HCFD review.
04/27/22 – TEI receives comments from HCFD on  04/18/22.  TEI incorporating comments and will deliver final draft to HCFD.
04/28/22 – Today’s discussion centered around adding to the study with a physicist recommendation on lead abatement protection. Champlin will lead collecting the information for the additional study and pulling in a third party person to help us update our report. Eventually, this will turn into a new report to the County. Meeting next Tuesday with THP, TEI and Champlin.
09/26/22 – TEI hand delivers (4) hard copies of the EMF report to HCFD.
10/26/23 – Project still on hold until further notice from HCFD.
12/12/24 – BW said to go ahead and send the final report to Rycca and close the project.
02/27/25 – OK to Archive.