03/24/21 – HCFD requests and TEI submits SOSS to provide Arc Flash Electrical System modeling and labeling at the Sheriff’s Heliport, the P&D Garage, and the Records Center. Project Pending SOSS approval and PO.
04/28/21 – Project Pending SOSS approval and PO.
5/26/21 – TEI receives signed SOSS and PO. TEI scheduling kickoff meeting with JN to begin field investigation and calculation phase of the study at all three facilities.
06/23/21 – TEI requests available fault information from Duke Energy for all 3 facilities. Upon receipt of data from Duke Energy, field work will be scheduled for each of the 3 facilities and studies will be completed.
07/28/21 – TEI receives data from Duke on Heliport and P&D garage, still waiting (and repeated requests) on Records Center Data. Upon receipt, we will schedule field work for input into models.
08/26/21 – Data from Duke still pending for record center. Multiple phone calls, when we talk to a rep, they pass along to someone else and the process starts over again.
10/26/21 – Data received from Duke. All buildings have been visited. Conn (EE on project) will schedule Phasor with Ian Zellner upon his return from vacation.
12/13/21 – site visits with EC to confirm feeder sizes etc. Finalize the model and submit to Charlie for final approval prior to application of labels.
02/23/22 – TEI submits finalized model calculations and report to CMI for review. We will schedule application of labels upon receipt of approval from Charlie.
04/27/22 – TEI receives CMI comments – and incorporated into the model. TEI printing labels on 04/27/22 and scheduling time with building manager to apply labels (week of 5/2/22).
05/26/22 – All labels complete and applied at building sites. Project complete.