PM: Matt Butz, Mike Barth
04/24/24 = TEI receives signed SOSS and PO.
05/29/24 – HCFD, Risk Mgmt and TEI meet to discuss scope and locations. TEI developing drawing package.
06/26/24 – TEI hand delivers drawings for HCFD to review.
07/24/2024 – HCFD moves location of NWS to 3rd floor data room. TEI updates the drawings.
08/28/24 – Project pending installation from DK.
10/30/24 – DK installs camera.
12/11/24 – TEI issues Punchlist. DK sends signed off punchlist to HCFD and TEI. Pending Closeout.
04/23/25 – TEI receives closeout documents from DK this week. Dayna is reviewing and assembling the binders.
05/28/25 – Finalizing binders.
06/25/25 – DK, DEG and HCFD to me re final closeout
07/30/25 – DEG received as builts from DK on 07/28/25. Record drawings are being completed and electronic copies of all will be delivered to HCFD.
09/24/25 – DEG delivers hard copies and thumb drive to HCFD. project complete.