Hamilton County Facilities

CH – Common Pleas AV Upgrades

PM: Megan, Mike Barth, Mike Murphy
04/24/24 – TEI receives signed SOSS and PO.
5/29/24 – HCFD, TEI and Judge Jenkins Visits Montgomery County CH to see system in action.  Champlin and TEI visit all courtrooms to develop plans and take measurements of existing benches for install locations of equipment.
06/26/24 – Weekly meetings are conducted every Wednesday afternoon.   The most current EV equipment has been sent from BIS to the team.  TEI has Design documents well developed and will be conducting a final walk thru of each of the courtrooms on 06/27/24 as soon as the docket clears.
07/24/24 – TEI will provide HCFD a final review set on 7/26/24. HCFD will review and get comments back to TEI by 8/2/24. Project to be issued for bidding on 8/7/24.
08/28/24 – Project has been issued for bidding. Prebid meeting was held on 08/23 – (2) bidders attended. Bid opening scheduled for 09/19.
09/25/24 – Received (1) bid from DK, (39% over budget). Rejected the bid, repackaged and re-issued for REBID. Rebid Prebid meeting scheduled for 10/18 and Bid opening on 11/06. TEI reaching out to area ECs by phone and notifying of bid opportunity.
10/30/24 – Final addendum issued on 10/30/24. Bid Opening 11/06/24 at 11:00 AM.
12/11/24 – Bids open. DK low bid. TEI vets the DK bid and sends letter or recommendation to HCFD. project pre-const meeting to occur upon contract approval.
01/29/25 – DK, HCMC, HCFD, BIS and TEI are in the pre-construction/procurement phase of the project. DK to provide project schedule.
02/26/25 – DK, HCFD, BIS, TEI and HCCPC have weekly meeting to update status and tracking.
03/26/25 – Work on CR 580 has started. Next CR’s were discussed at the meeting this week. BIS to ship the next 2 rooms equipment week of 4/10.
04/23/25 – Work continues in CR 580. End of this week DK to be ready for carpet install (HCFD covering carpet install). Floor slab xray scheduled for 04/26/25 (Saturday).
05/28/25 – BIS sends technician to CR 580 today for coordination with DK. All DK field issues/concerns addressed. Field visit to fire up the system on 05/30 at 1:00 PM.
06/25/25 – CR 580 complete, pending training on equipment and demo to other Judges.
07/30/25 – CR 580 training completed. CR 580 in use and DK is now working on CR 320. Tweaks are happening as the systems are being placed into service. Rycca asked if we should order the AV equipment and set it back in the Archive room and they can use them out of the boxes on the sixth floor. Punchlist scheduled for 8/5 at 3PM.
08/27/25 – Punchlist for room 580 completed. DEG issues the Punchlist to DK. Installation of BIS equipment installed this week.
09/24/25 – Finalizing CR320. Moving on to CR 380 next. At const meeting, it was discussed to ship all equipment as soon as ample storage space for 16 more rooms equipment. Arpa funds must all be spent by 12/31/2026.
10/29/25 – Programming installed in Room 320. Work starting in rooms 300 and 380.
12/10/25 – Work continues with CR 300 and 380. Punchlist scheduled for 12/10/25 cancelled due to court session running long.
01/28/26 – Project continues.at the meeting today discussed the next 2 rooms to be worked on (340 and 360). This will finish the CRs on the 3rd floor.
02/25/26 – Project continues. Work on 3rd floor progressing. Speakers swapped out in 580 and sound quality substantially improved. DK brings in “sound expert”, Leo Little form ICS, to evaluate rooms. Leo to provide quotation to DEG for sound engineering services.
03/25/26 – Electrician changes necessitated for the project. DK to update situation ASAP. finishing CR 330 and moving to 360 and 340 next.
04/29/26 – Work continues in Rooms 340 and 360. Walk for 485 and 496 scheduled for 5/5.
05/27/26 – work continues in room 340 and 360. Rooms 485 and 495 are next (waiting on floor boxes to be fabricated). Walking locations on the 5th floor 05/27/26.
06/23/26 – Sound Guy (Leo Little) models room 485 and returns proposed layout with the speakers that were purchased from BIS.
07/29/26 – Sound guy visits room 300, modelling the room. HC directs Leo to only use the bill of materials for the rooms, and to not give recommendations for improved sound quality with equipment not in the original BOM.
08/26/26 – Room 300 sound recommendations installed. Sound quality greatly improved. ICS states that next 2 rooms are scheduled to be sent today.
09/23/26 – Work continues on the installation. ICS completes all room sound models and recommendations. There are 2 rooms (320 and 380) that HCFD sent comments back to ICS for tweaks.
10/28/26 – All sound models received on all rooms. Punchlist walk occurred on 10/26/2026. Work starting on Jenkins CR on Monday 11/02.

Scroll to Top