Hamilton County Facilities

CH – Additional Flagpoles

07/10/20 – On site review. Authorized to proceed on CH only.
08/27/20 – One and Two flagpole settings discussed.
09/09/20 – Estimate and cut sheets uploaded on to Archibus.
10/29/20 – Approved to proceed on adding two flagpoles at Courthouse. Need to measure actual height of existing pole.
11/20/20 – RFP sent to Megen Construction, James Hunt Construction and Triton Services.
11/24/20 – Prebid Meeting at Courthouse.
12/01/20 – Addendum 1 issued.
12/08/20 – Bids received. Triton is apparent low bidder.
12/09/20 – Zoom meeting with Triton to review scope and vet bid. Official Letter of Recommendation sent to County.
01/22/21 – John Nester sent signed contract to Josh Smallwood at Triton.

02/25/21 – Josh Smallwood to deliver Schedule of Values, Project schedule and Submittals mid week of 3/1

03/11/21 – Permit issued. Waiting on approval. Still need lighting submittal.

04/29/21 – Waiting on Triton to answer foundation question for permit response and physical samples for flagpole material.

04/29/21 – THP to provide structural drawing for footing design

05/10/21 – THP provided Champlin with structural sketch

05/21/21 – THP provided Champlin with official design.

06/08/21 – Construction kick-off meeting. still waiting on additional finish sample from Josh.

07/19/21 – Notice to Proceed issued to Triton.

08/24/21 – Submittal returned to Triton.

10/05/21 – Site visit attended by County, Triton and Admiral. led to confusion on total scope.

10/25/21 – Meeting with Triton confirmed scope and gave Triton direction.

11/27/21 – Boring for the hole started. Soil conditions were found to be unacceptable. Terracon was contacted by THP to analyze soil conditions. No schedule has been given for the analysis.

01/26/22 – Ongoing communication between Triton THP and Terracon. Pricing to be submitted for added services.

02/23/22 – Change Order #1 signed and returned.

03/31/22 – Triton waiting on sidewalk permit to restart construction.

04/28/22 – Triton has provided an install schedule from 4/30 to 5/7 with installation complete on the 7th.

05/26/22 – Project Completed. Punch to be scheduled soon.

06/30/22 – Reviewed on site. Official punch to be submitted to triton shortly.

07/28/22 – Punchlist to be issued.

08/25/22 – Punchlist items complete. Final pay app to be submitted.

09/29/22 – Waiting for Triton to submit closeout documents

10/27/22 – Close out documents missing warranties and O&M manuals. Triton working on it.

12/15/22 – Close out documents received.
02/23/23 – OK to Archive.

Scroll to Top