08/20/20 – SOSS signed and returned. Initial provider meetings starting this week.
08/25/20 – 09/15/20 CA, CMTA, GBBN visit all shelter sites.
09/17/20 – 09/22/20 CA, CMTA, GBBN zoom meetings with all property managers to confirm scope of work.
09/22/20 – GBBN provides CA with SD drawings for CA to proceed with implementation.
09/23/20 – CA provides Messer with preliminary drawings for pricing.
09/28/20 – Target date for getting Messer final drawings for pricing.
10/29/20 – Bid packages and Permit ready. Waiting for authorization to proceed.
12/10/20 – Waiting for Authorization to proceed
01/26/21 – Meeting with Lisa Webb and City of Cincinnati to reassign Champlin contract.
02/25/21 – No update. Final stages of dividing contract between county and city.
03/25/21 – No Update
04/29/21 – No Update
05/18/21 – Meeting with City to discuss scope and remaining fee.
06/07/21 – Final signed assignment agreement received.
07/27/21 – Contract transfer complete.
08/26/21 – Project no longer a County project.