07/21/20 – First field trips for the Covid HVAC study scheduled.
08/12/20 – First draft of the report submitted for review.
08/21/20 – First draft of the report resubmitted and comments returned.
08/20/20 – Started integrating the Portable HEPA filtration units into the report and finding truly equal manufacturers, lead times, and cost.
08/21/20 – Final Study Report submitted to County with floor plans.
08/23/20 – BW asked to break out the building improvements and send to Tony for each building manager. Send directly to Tony Matre.
08/27/20 – Reports were well received with the County. Phase 2 for HEPA placements and safety PM coming up next.
09/14/20 – Sent building reports to Tony Matre and final information to Prosecutor Office. Answered some additional questions for the prosecutor this week and followed up on some additional articles emailed to me.
06/26/20 – Sent touchless water review to County for review of Ameresco proposal.
10/01/20 – Bid questions sent to bidders who submitted bids on the Portable HEPA Units.
10/05/20 – PO was release to the vendor for the purchase of Portable HEPA units.
10/06/20 – ThermalTech released building Recommendations to Tony Matre for Bldg Mgr use.
10/09/20 – Created cross reference guide for filter replacements from Tony
10/13/20 – County asked for SOSS for PM creation for the HEPA filtration units.
10/28/20 – Safety consultant has submitted a price to TTC to update our SOSS for the PM work on this project.
12/04/20 – Talked to Bert and Joe this past week about delivery of the HEPA units. The UV lights are on a delayed delivery schedule. We are seeing how this affects equipment.
12/30/20 – Working on excel format for equipment PM.
01/15/21 – TTC talks to Tim Schuh about setting up unit PM for this job.
01/21/21 – HEPA units are arriving disassembled. Joe sends serial numbers to TTE.
01/26/21 – TTC sends email response to RWL request for BOMA review.
02/19/21 – TTC commissioned Comm Center Unit to final CFM and moved closer to the plug. Gave county option for the longer plug if needed.
02/24/21 – TTC and RAJ commissioned 230 East 9th & 2020 HEPA units. One HEPA at 2020 has been sent back to the factory for repairs. We will be visiting the other sites in the next two weeks.
02/25/21 – BW asked for TTC email to be rolled up into a memo, general update and usage, add Charlie safety to PM, add Komisky report as an appendix to the memo.
03/25/21 – All buildings CX fieldwork is complete. Several units have had additional issues and CAI has visited the buildings to troubleshoot. Two have to be fixed by the factory, one was reprogrammed in the field and that data shared with building managers for future troubleshooting. TEI starting on the final CX summary report.
04/29/21 – Bert revised the worksheet and request ThermalTech to get all final serials numbers for the remaining units. TTC dispatched Ryan to collect the information.
05/26/21 – This month we retrieved the rest of the serial numbers on the HEPA units, filled out, and sent in the equipment worksheet for Archibus. We assisted with some problem units at 2020 and TPC and we visited the Law Library and provided a recommendation on units in the Law Library.
06/25/21 – Final worksheets were sent to the County on Admin 6th floor waiting and BOCC meeting room and 2020 Multipurpose Rooms. Teh final equipment list including missing serial numbers is in.
07/28/21 – DEV PM entered for County review and comments were sent back this week. We are ready to move to actual PM for these entries. LOTO safety procedures can be uploaded as a PDF with the PM to be performed.
08/25/21 – TTC visited 800 Broadway 6th floor today and took field measurements. Created worksheets and sent out floor plan to facilities. HEPA units not required in this space per the existing HVAC serving this area.
10/28/21 – TTC submits recommendations for the Ohio Means Jobs building. All PMs were uploaded to Archibus on 10/5/21.
10/28/21 – Portable HEPA units PM are uploaded and ready for November 1. Tony found better filter pricing for these units.
11/09/21 – Covid report sent to Rycca for A&D 2nd, 4th, and 5th-floor lobbies. None of these spaces required additional Portable HEPA at this time.
01/22/22 – The lower level study for OMJ is complete and we did add one Portable HEPA in this space.
07/27/22 – No updates to the Covid study this month.
02/22/23 – Met with Rycca and Glen on A&D conference room Covid needs. Backed existing unit down to 100 to 200 cfm each per new calculation worksheet.
04/26/23 – No updates but in May the emergency mandate may expire and we will address the use of the Portable HEPA during that time.
05/21/23 – Units were removed from operation this week in some buildings.
06/28/23 – Update Ralph et al. on Covid updates from his email. No changes necessary.