PM = Tony Matre, Mike Barth
10/30/24 – TEI submits SOSS for approval. Project pending SOSS approval and PO.
12/11/24 – TEI receives signed SOSS and PO. Per Tony – Project to commence Q1 of 2025
01/29/25 – TEI and Matre meet to establish project schedule. Project in process.
02/26/25 – No updates this month
03/26/25 – TEI visits all building sites that are new to inventory/coming online this spring/summer. TEI submits DEI paperwork. As soon as approved by DEI – ITB will be issued.
04/23/25 – TEI issues project for bidding. Prebid meeting was on 04/21/25. In bidding phase.
05/28/25 – Bids received. (2) bidders. Project in contract phase.
06/25/25 – Project in contract phase.