PM = Tony Matre, Mike Barth
10/30/24 – TEI submits SOSS for approval. Project pending SOSS approval and PO.
12/11/24 – TEI receives signed SOSS and PO. Per Tony – Project to commence Q1 of 2025
01/29/25 – TEI and Matre meet to establish schedule. Project in progress.
02/26/25 – No updates this month. AKM wants bid out in April ’25
03/26/25 – No updates this month. Work to occur in April 2025.
04/23/25 – Nick (TEI) developing and updating the data sheets for the buildings with newer systems. XBE paperwork in works and ITB to be issued.
05/28/25 – No updates
06/25/25 – No Updates
08/27/25 – DEG going to issue bid package first week of September. Proposed (AKM approved) prebid dates are 9/15 and 9/16.
09/24/25 – DEG issues for bidding. JCI, Siemens and SA Communale indicate interest in project. Prebid dates are 09/23 and 09/24, no bidders attended the prebid walk thrus. bid openings 10/22.
10/29/25 – SA Communale Only bidder. AKM working on Contract.
12/10/25 – Project in contract phase.