Hamilton County Facilities

All Bldgs-A

All Buildings – Generator Systems Inspections and Testing

PM = Tony Matre, Mike Barth

10/30/24 – TEI submits SOSS for approval. Project pending SOSS approval and PO.
12/11/24 – TEI receives signed SOSS and PO. Per Tony – Project to commence Q1 of 2025
01/29/25 – TEI and Matre meet to establish project schedule. Project in process.
02/26/25 – No updates this month
03/26/25 – TEI visits all building sites that are new to inventory/coming online this spring/summer. TEI submits DEI paperwork. As soon as approved by DEI – ITB will be issued.
04/23/25 – TEI issues project for bidding. Prebid meeting was on 04/21/25. In bidding phase.
05/28/25 – Bids received. (2) bidders. Project in contract phase.
06/25/25 – Project in contract phase.

All Buildings – Generator Systems Inspections and Testing Read More »

All Buildings – Fire Alarm System Inspections & Testing

PM = Tony Matre, Mike Barth

10/30/24 – TEI submits SOSS for approval. Project pending SOSS approval and PO.
12/11/24 – TEI receives signed SOSS and PO. Per Tony – Project to commence Q1 of 2025
01/29/25 – TEI and Matre meet to establish schedule. Project in progress.
02/26/25 – No updates this month. AKM wants bid out in April ’25
03/26/25 – No updates this month. Work to occur in April 2025.
04/23/25 – Nick (TEI) developing and updating the data sheets for the buildings with newer systems. XBE paperwork in works and ITB to be issued.
05/28/25 – No updates
06/25/25 – No Updates
08/27/25 – DEG going to issue bid package first week of September. Proposed (AKM approved) prebid dates are 9/15 and 9/16.
09/24/25 – DEG issues for bidding. JCI, Siemens and SA Communale indicate interest in project. Prebid dates are 09/23 and 09/24, no bidders attended the prebid walk thrus. bid openings 10/22.
10/29/25 – SA Communale Only bidder. AKM working on Contract.
12/10/25 – Project in contract phase.

All Buildings – Fire Alarm System Inspections & Testing Read More »

All Buildings – Fire Sprinkler Inspection & Testing 2025

PM: Tony Matre, Terry Cannon

09/26/24 – SOSS Requested.
10/30/24 – SOSS submitted. Preliminary project setup has begun. TTE needs to add three buildings to the bid this time around, 111, 525, 4210 Dane, Crime Lab and Coroners Office.
12/12/24 – Approved SOSS and PO not received yet.
01/28/25 – PO received. Preliminary specs assembled by Barrett. We need to scheduled fieldwork to confirm quantities. We heard the first deadline for draft review is end of February.
02/26/25 – Limited updates, we will be working on this one in March.
03/25/25 – No updates. We still plan on bidding this job by end of April.
04/23/25 – Fieldwork is completed. New buildings are added, old buildings are removed. Specs have been updated for 2025 Code references. The Project manual is ready for Tony Matre review.
05/28/25 – TTC compiling proposed bid cost to request the ITB number for this project. Trying to scheduled a two day prebid for this project. Bid will be in June.
06/25/25 – Prebid meetings scheduled for July 9,10.
07/21/25 – Addendum #1 sent to bidders.
08/28/25 – Bids opened and awardable. SA Comunale had only openable bid. Next steps by County.
09/24/25 – Contract being drafted. We answered some questions about the give year testing.
10/29/25 – Archive.

All Buildings – Fire Sprinkler Inspection & Testing 2025 Read More »