PM = John Nester, Mike Barth
08/28/24 – ThermalTech submits SOSS for approval.
09/25/24 – TEI receives signed SOSS and PO. TEI contacts Bldg Mgr to schedule site eval (tentatively 9/30 or 10/1).
10/30/24 – TEI submits report for review and comments from HCFD.
12/11/24 – TEI develops drawings for County review.
02/26/25 – TEI develops permit documents and HCFD solicits quote from Glenwood (emergency on call electrician), Glenwood submits drawings for permit.
03/26/25 – Plan review complete and approved. Glenwood pulls electrical permit and to schedule install.
04/23/25 – Glenwood proceeding with the removal of the raceway and installation of the new conduit system. HCFD to notify TEI when complete and a punchlist visit will be conducted.
05/28/25 – Project completion pending punchlist.
06/25/25 – HCFD and TEI complete punchlist. No items identified on punchlist. Project complete.