Hamilton County Facilities

Animal Shelter-A

Colerain – Animal Shelter Wood Canopy (F020)

PM: John Nester, John Millar
10/21/24 – HC reached out to THP asking for repair of the Animal Shelter Wood Canopy.
10/31/24 – THP reviewed internal past documents and County email. THP to meet with County to discuss next steps.
12/11/24 – THP working on repair design.
12/16/24 – THP surveyed the site and met with County personnel. Shoring configuration was discussed and direction was given to install preliminary shoring.
12/17/24 – THP sent shoring detail for review.
12/19/24 – HC installed shoring and sent photos of sample shores. Shoring detailing was confirmed.

Colerain – Animal Shelter Wood Canopy (F020) Read More »

Colerain – Animal Shelter Boiler Replacement

PM: Tony Matre, Terry Cannon

09/26/24 – After SD and pricing efforts, we have decided to bid this project via Small Project bid with one for one like boiler and no recirculation pump replacements in the Base Bid.
10/30/24 – Drawing are modified and ready for bidding. NKY will be but no word back from DK and Geiler on their willingness to give us a price for this work.
12/12/24 – No updates since last meeting. BW said to go ahead and get three prices for the boiler replacement but they are not moving on doing the work this year. One price received so far.
01/28/25 – No updates.
02/26/25 – No updates.
03/25/25 – No updates.
03/26/25 – Tony confirmed this project on hold. No work for TEI at this time.
04/23/25 – Project on hold.
05/28/25 – Archive until further notice.

Colerain – Animal Shelter Boiler Replacement Read More »

Colerain – Animal Shelter Electrical Investigation

PM = John Nester, Mike Barth
08/28/24 – ThermalTech submits SOSS for approval.
09/25/24 – TEI receives signed SOSS and PO. TEI contacts Bldg Mgr to schedule site eval (tentatively 9/30 or 10/1).
10/30/24 – TEI submits report for review and comments from HCFD.
12/11/24 – TEI develops drawings for County review.
02/26/25 – TEI develops permit documents and HCFD solicits quote from Glenwood (emergency on call electrician), Glenwood submits drawings for permit.
03/26/25 – Plan review complete and approved. Glenwood pulls electrical permit and to schedule install.
04/23/25 – Glenwood proceeding with the removal of the raceway and installation of the new conduit system. HCFD to notify TEI when complete and a punchlist visit will be conducted.
05/28/25 – Project completion pending punchlist.
06/25/25 – HCFD and TEI complete punchlist. No items identified on punchlist. Project complete.

Colerain – Animal Shelter Electrical Investigation Read More »

Animal Shelter – Dane St Renovations

Project Managers: Mike Murphy, Bert Watts
05/26/22 – SOSS requested to move forward with design. BW provided updated scope for access to the Animal Shelter buildings.
06/30/22 – SOSS approved for Northside building to be converted to animal shelter. Preliminary schedule provided to County. Site visit to be scheduled.
08/25/22 – Site visit performed. Held user meetings to define scope. Work in progress.
09/25/22 – ThermalTech directed to submit their own SOSS’s for this project for regular and small scopes.
09/29/22 – Conceptual plan and estimate to be submitted 9/30
09/29/22 – TEI SOSS has been submitted to BW for approval.
09/30/22 – Conceptual plan and estimate submitted to County.
10/27/22 – ThermalTech electrical & mechanical cost estimates are done. We are working on drawings and plumbing estimates now.

12/15/22 – SD plans and estimates complete

01/26/23 –  No Update

02/22/23 – No Update

03/30/23 – No Update

04/27/23 – No Update

05/25/23 – No Update

Animal Shelter – Dane St Renovations Read More »

Animal Shelter – Master Planning

PM: Mike Murphy, Bert Watts
07/29/21 – Master Planning meeting being scheduled for scope and SOSS creation.
08/23/21 – Meeting held with County and Animal Shelter representatives
08/25/21 – Animal Shelter CEO puts Champlin in touch with Animal Arts.
10/17/21 – SOSS submitted to County. Waiting Approval.
11/08/21 – Approved SOSS received.
11/29/21 – Kickoff meeting held. attended by Champlin, County and Cares.
12/06/21 – Programming meeting held. Attended by Champlin, County and Cares. Finalized schedule and future meeting.
01/17/22 – Concept plan approved.
01/26/22 – Bi-weekly meetings in progress. Floor plan and renderings begun.
02/24/22 – Final user meeting to confirm/present interior and exterior renderings
04/11/22 – Final deliverable submitted to County.
04/13/22 – SOSS submitted for analysis of two existing buildings.
04/21/22 – CH and County Meeting to review commissioner feedback.

01/26/23 – Fair grounds site evaluated for animal shelter location. Fit plans in progress.

02/22/23 – SOSS approved to review Winton road site for test fit.

03/30/23 – No update.

04/27/23 – No update.

05/25/23 – No update.

06/29/23 – No update.

Animal Shelter – Master Planning Read More »

Animal Shelter – Roof Replacement

05/21/21 – Hamilton County requested SOSS for the roof replacement of two roofs with alternates.
06/03/21 – THP provided SOSS for roof replacement project.
06/15/21 – County approved SOSS.
08/02/21 – THP visited site to survey and document existing conditions.
08/16/21 – THP issued Opinion of Probable Costs to Hamilton County for project budget approval.
08/20/21 – THP issued progress drawings and project manual for Owner Review.
08/25/21 – THP visited site to review condition of exposed decking in office and verify conditions at Entry canopy.
09/01/21 – THP received and reviewed AIA contract documents for project manual.
09/02/21 – THP met Hamilton County at site to review drawings and confirm scope of work items and Alternates.
09/03/21 – THP finalized and issued documents for bid.
09/09/21 – THP received and replied to substitution request email from roofing supplier and updated specifications.
09/14/21 – THP led pre-bid meeting at Animal Shelter.
09/15/21 – THP developed pre-bid meeting notes and issued Addendum 01.
10/05/21 – Bid opening. Received bids from Ace Exteriors, Wm. Kramer & Son, and Imbus Roofing.
10/06/21 – THP had conversations with Ace Exteriors to qualify bid, discuss pricing for canopy replacement, and request references and manufacturer’s certifications.
10/08/21 – THP finalized letter to Hamilton County summarizing bid process and recommending award to Ace Exteriors, including Base Bid and Alternate 1 scopes of work.
10/08/21 – THP responded to email from Hamilton County summarizing reasons bids received for canopy exceeded original estimates.
10/18/21 – THP received and began review of roofing products received from contractor as substitutions due to material availability.
10/20/21 – THP had conversation with Contractor and emailed Hamilton County about status of registering Ace Exteriors as a vendor.
10/21/21 – THP received from Contractor and forwarded to Hamilton County completed Substitutions form missing from bid proposal.
10/28/21 – THP issued revised title sheet with wind load information for Office/Admin. and Cat House roofs and requested Contractor review with manufacturer the potential implications on warranty and adhesive requirements.
11/05/21 – THP had conversation with Hamilton County to discuss material substitutions proposed by Ace Exterior due to material availability and schedule issues.
11/05/21 – THP had conversations with Wm. Kramer & Son about material availability and confirmed they would not be able to provide the specified roof insulation and cover board by spring 2022.
11/05/21 – THP emailed Hamilton County recommendations to proceed with the project using the substitute materials proposed by Ace Exteriors.
11/10/21 – Hamilton County emailed contract to Ace Exteriors.
11/23/21 – Ace Exteriors emailed Hamilton County the signed contract, worker compensation certificate, and a project-specific certificate of liability insurance.
12/23/21 – Hamilton County emailed the signed contract and PO to Ace Exteriors and requested development of required preconstruction documents.
01/28/22 – THP emailed Contractor about status of materials order, development of required pre-construction documents, completion date, and additional details to be developed.
02/01/22 – THP emailed Contractor draft of revised roof plan and details showing contract scope and new details at interface between project scope and canopies to remain.
02/04/22 – THP finalized and issued revised documents for Permit and Construction.
02/10/22 – THP reviewed and returned product submittals for roofing materials.
03/08/22 – THP received and reviewed Contractor’s pricing and lead time information for aluminum v. galvanized edge metals.
03/10/22 – THP had conversation with County about approval of proposed metal substitution due to increased costs and lead time issues, and re-reviewed submittals for roof specialties.
04/05/22 – Preconstruction meeting.
04/12/22 – THP issued minutes from preconstruction meeting.
04/12/22 – THP reviewed submittals and requested revised insulation layout.
04/13/22 – THP had conversation with Contractor about discrepancy in slope of tapered insulation between documents and submitted revised insulation layout, and retuned submittal with exceptions noted.
04/13/22 – THP had conversation with Contractor about installation issues and additional cost of taller fascia that would be required with 1/4″ slope tapered insulation v. 1/8″ slope indicated in documents. Contractor to request updated/revised tapered layout to reflect the 1/8″ slope.
04/19/22 – THP received, reviewed, and returned re-revised insulation layout submittal.
04/22/22 – THP had conversations with Contractor and Hamilton County to discuss delayed start date due to weather and insulation slope issue, and emailed team about rescheduling first progress meeting.
05/02/22 – THP met project team at site for progress meeting and site visit to document progress.
05/02/22 – THP emailed Contractor a link to a shared folder containing original construction drawings.
05/02/22 – THP developed and issued minutes from progress meeting #1.
05/03/22 – THP issued field report 01 from 5/2 site visit.
05/03/22 – THP reviewed pencil copy of Contractor’s first application for payment and replied with comments.
05/03/22 – THP reviewed and approved notarized copy of Contractor’s first application for payment and forwarded to Hamilton County.
05/12/22 – THP met Contractor on site to review and document progress.
05/15/22 – THP issued field report 02 from 5/12 site visit.
05/16/22 – THP met project team at site for progress meeting and site visit to document progress.
05/20/22 – THP developed and issued minutes from progress meeting #2.
05/20/22 – THP issued field report 03 from 5/16 site visit.
05/24/22 – THP visited site to review and documented completed installation of EPDM.
05/26/22 – THP issued field report 04 from 5/24 site visit.
06/01/22 – THP reviewed Ace fascia and coping profiles submittals.
06/29/22 – Progress meeting and site visit scheduled to review installed drains and progress of edge metal installation.
07/22/022 – THP visited site to do final inspection of completed work and identify punchlist items.
07/25/22 – THP published field report and punch list for roof work from 7/22/22 visit.
08/09/22 – THP emailed Contactor about status of completing punchlist items.
08/09/22 – THP developed Change Order #1 for unused Cash Allowance and Unit Price credit and forwarded to Contractor for signature.
09/21/22 – Contractor emailed team about status of completing punchlist.
09/26/22 – THP emailed Contractor about acceptance of remaining two punchlist items, status of second application for payment, closeout documents, and approval of Change Order #1.
10/28/22 – THP visited site to confirm completion of punchlist items, and emailed Contractor about the status of closeout documents, approval of Change Order #1, and the application for payment #2 for substantial completion.
11/09/22 – THP replied to email from Contractor rejecting request for additional use of Cash Allowance.
11/18/22 – Contractor provided preliminary closeout documents for THP’s review.
11/21/22 – Change Order #1, a credit for unused Unit Price Repairs and Cash Allowance, was signed by Contractor and Hamilton County.
12/01/22 – THP reviewed Contractor’s preliminary closeout documents and replied with revisions to be made and additional documents to be provided.
12/07/22 – Contractor provided revised closeout documents for THP’s review.
12/12/22 – THP reviewed revised closeout documents and emailed Contractor to proceed with providing hard copies, including notarized legal documents and the project binder.
01/03/23 – THP reviewed Contractor’s hard copies of closeout documents and project binder and requested revised as-built drawings using permit set as basis for markups.
01/04/23 – THP received revised as-built drawings, emailed Hamilton County a link to a shared folder containing digital copies of all closeout documents, approved Contractor’s second and final application for payment, and delivered project binder.
02/23/23 – OK to Archive.

Animal Shelter – Roof Replacement Read More »

Animal Shelter – Kennel HVAC Modifications

03/24/21 – AKM requests SOSS for the installation of mini-split HVAC systems for (2) kennels. TEI is authoring and will submit by end of the day 03/26/21.
04/28/21 – SOSS submitted. Project completion pending SOSS approval.
05/26/21 – TEI receives signed SOSS and PO. TEI completes drawings and submits to IBI for Plan review. Plan review approved and TEI applies for permit. Installation work to be coordinate with Trades and building manager.
06/23/21 – Permits received. Work installed. Upon repair of boards in the units (due to pest infestation, electronics were compromised), final inspections will occur.
07/28/21 – Repairs have been completed and ready for TEI to call IBI and Schedule a final. TEI coordinating with Trades and IBI and will schedule in the next few days.
08/26/21 – IBI final inspection scheduled for 08/27/21. Time TBD, per IBI standards, must call day of the inspection to get timing. TEI coordinating with John Kleeman and John Nester.
10/26/21 – IBI required to have HVAC permit prior to the final for IBI. TEI developed HVAC documents and are awaiting permit approval and inspection to re-schedule the IBI final.
12/13/21 – Plan review and zoning have verbally approved.  TEI was told full approval for the HVAC permit will be approved on 12/17/21.  Once approved and picked up, we can have inspection, approval, and then have IBI final inspection.
01/25/22 – HVAC plans approved.  Need to schedule final HVAC inspection and also final IBI
02/23/22 – Per building manager – 3 out of 4 units not functioning currently due to rodent issues.   building manager will contact TEI when the units are operational so that we can schedule the finals.
04/27/22 – inspections pending units being operational.
05/26/22 – HVAC inspection complete/passed.  IBI pending repairs to work by NK heating and Air.  Building manager to notify TEI when we can schedule final.
06/28/22 – IBI pending repairs to work by NK heating and Air.  Building manager to notify TEI when we can schedule final.
07/27/22 – IBI PASSES inspection!  Project complete!

Animal Shelter – Kennel HVAC Modifications Read More »

Animal Shelter – Exit Signs

01/06/21 – SOSS signed and received.
01/21/21 – Champlin and TTE walkthrough with John Nester to review existing locations and review scope.
02/09/21 – Champlin uploaded Estimate to Archibus.
02/25/21 – TEI needs to add cost to Archibus for this project.
03/02/21 – All estimates are uploaded. Final report to come.
04/29/21 – Estimates are in and final report uploaded to Archibus.
05/27/21 – No Update. OK to Archive

Animal Shelter – Exit Signs Read More »

Animal Shelter – Trailer Power and Signal

12/09/20 – AKM called ThermalTech to develop Opinion of Probable cost and opinion of engineering fees to communicate to Animal Shelter personnel. AKM to advise TEI if the Animal Shelter wants to proceed with project, at which point AKM to ask for an SOSS. TEI sent opinions of cost to AKM on 12/04/20.

01/26/21 – Trailer delivered to site. TEI speaks with AKM about moving forward. AKM requested revised cost data based upon the location where the trailer was placed. TEI sends AKM data requested and asks about next steps

01/28/21 – Discussed having Duke pulling a separate service for this trailer to keep it separate from the main building’s supply. TEI stated that is how it is planned at this time.

02/23/21 – AKM requests SOSS for design work for the trailer install. TEI sends to AKM.

03/24/21 – Project pending SOSS approval and PO.

Animal Shelter – Trailer Power and Signal Read More »

Animal Shelter – Arc Flash Study

09/18/20 – New Arc Flash project SOSS sent to County, followed up with some additional drawings to Tony from study. This project can probably be archived.
09/24/20 – Approved SOSS has been received. Arc Flash to begin.
12/09/20 – Duke Energy information finally received from Duke, and model is developed. Site visit to coordinate and confirm existing conditions to be scheduled ASAP (post quarantine).
01/26/21 – TEI conducts field survey, develops model and is finalizing the model. Model results to be sent to Charlie at CMI for review no later than 01/29/21.
02/23/21 – TEI completes model and sends to Charlie at CMI for review and comments. Upon receipt of Charlie’s comments, TEI will implement, print and apply labels.
03/24/21 – TEI receives and incorporates comments from CMI. Model completed and labels are printed and TEI is scheduled to apply labels week of 03/29/21.
04/28/21 – Labels applied. TEI to submit printed results to HCFD and the project is complete.
05/26/21 – Project complete. OK to Archive