12/09/20 – AKM called ThermalTech to develop Opinion of Probable cost and opinion of engineering fees to communicate to Animal Shelter personnel. AKM to advise TEI if the Animal Shelter wants to proceed with project, at which point AKM to ask for an SOSS. TEI sent opinions of cost to AKM on 12/04/20.
01/26/21 – Trailer delivered to site. TEI speaks with AKM about moving forward. AKM requested revised cost data based upon the location where the trailer was placed. TEI sends AKM data requested and asks about next steps
01/28/21 – Discussed having Duke pulling a separate service for this trailer to keep it separate from the main building’s supply. TEI stated that is how it is planned at this time.
02/23/21 – AKM requests SOSS for design work for the trailer install. TEI sends to AKM.
03/24/21 – Project pending SOSS approval and PO.