2020 – Emergency Gear Upgrade Replacement
PM = Tony Matre, Mike Barth
10/28/2026 – HCFD requests SOSS.
2020 – Emergency Gear Upgrade Replacement Read More »
2020 Auburn
PM = Tony Matre, Mike Barth
10/28/2026 – HCFD requests SOSS.
2020 – Emergency Gear Upgrade Replacement Read More »
PM – Tony Matre, Mike Barth
10/28/2026 – HCFD requests SOSS.
2020 – ATS Replacement Read More »
PM: Rycca Thacker, John Millar
07/29/21 – THP Submitted SOSS to County.
08/23/21 – SOSS approved.
02/2321 – THP completed roof cuts and assessments. THP scheduling masonry survey for repairs, anticipated week of 2/28.
03/07/22 – Week of March 7th, THP Surveyed interior for masonry distress and slab settlement.
03/24/22 – THP and County reviewed field findings from THP survey.
04/27/22 – THP developing DD documents.
06/30/22 – THP developing DD documents. Plan to bid mid August.
07/28/22 – THP proposed design schedule update DD issue 8/30/22 and CD issue 9/15/22
10/27/22 – THP to publish 90% drawings 10/28/22.
01/10/23 – County provide review comments.
01/26/23 – THP anticipates CD documents issued 2/3/23.
02/23/23 – Finalizing documents. Plan to issue bid documents week of 2/26.
03/24/23 – Bid documents anticipated the week of 4/3/23.
05/31/23 – Documents advertised for bid.
06/07/23 – Prebid mtg occurred.
06/16/23 – Addendum No. 1 issued.
06/27/23 – Bid opening occurred. Two submitted bids received with low bid 16% above advertised budget. THP to review with County next steps.
08/31/23 – June bids rejected. County requested roof and masonry project be separated and bid this fall. THP published review documents 8/31/23.
10/06/23 – Roof Repair project approved for KEE system. AIA documents issued to THP. Slab and Masonry Repair project approved. AIA documents issued to THP.
10/0923 – County comments to the review documents published to THP.
10/09/23 – Inclusion goals published.
10/12/23 – Review Bid Documents published for both the Roof and Slab Lifting Projects.
10/13/23 – Final Bid documents published for both the Roof ITB 116-23 and the Slab Lifting and Masonry Repairs ITB 117-23 projects.
10/16/23 – Roof and Slab projects advertised for bid.
10/25/23 – Prebid meeting occurred for both projects.
10/26/23 – Bid opening scheduled for November 30, 2023.
11/09/23 – Slab and Masonry Repairs Addendum No. 1 issued.
11/13/23 – Roof Repairs Addendum No. 1 issued.
11/14/23 – Slab and Masonry Repairs Addendum No. 2 issued.
11/17/23 – Roof Repairs Addendum No. 2 issued.
11/20/23 – Roof Repairs Addendum No. 3 issued.
11/30/23 – Slab and Masonry Repairs Bid opening. No submissions.
11/30/23 – Roof Repairs Bid opening. Five contractors submitted bids with a range of $1,761,452 to $2,103,895. One bid was below advertised bid amount and the remaining bidders were within 10%. Bids sent to the economic inclusion department for review.
12/23/23 – Kelly Brothers Roofing found responsive and THP notified to review the bid.
01/08/24 – THP and Kelly Brother’s reviewed the bids.
01/15/24 – THP published bid summary recommending Hamilton County contract with Kelly Brothers for the roof project.
02/06/24 – Hamilton County sent AIA contract to Kelly Brothers Roofing.
03/02/24 – Kelly Brothers returned contracts to Hamilton County.
03/25/24 – THP published conform and permit drawings to Kelly Brothers and Hamilton County. Drawings updated with 2024 code review and requirements.
03/27/24 – Project contract goes before the board on April 4th for final approval.
04/11/24 – Executed contract sent to KBR.
04/29/24 – Preconstruction meeting completed.
05/30/24 – Project update – THP processing submittals and shop drawings.
05/31/24 – Initial scaffolding installation for roof access to start.
04/29/24 – Preconstruction meeting occurred.
05/31/24 – Project mobilization occurred.
06/27/24 – Contractor working on Roof D, E, and F. Existing roofing removed, repairs started and installation of the complete system started on roof D south end. Roof work on hold until July 1.
07/25/24 – KBR working on Roof D installing system south to north. Temporary scaffolding stair tower at roof F extended to roof D. Temporary stair tower and bridge installed to Roof C.
08/16/24 – THP published Bulletin No. 1.
08/29/24 – KBR completed main installation of Roof D and working on detailing. Preparation for Roof E installation has started.
08/29/24 – KBR completed main installation of Roof D and working on detailing. Preparation for Roof E installation has started.
09/12/24 – THP published walk mat layout review drawing.
09/16/25 – THP sent SOSS for additional services for Roof Safety Design.
09/19/24 – KBR completed main installation on roof D and E and working on detailing on both. Preparation for Roof F has started.
09/19/24 – THP published roof safety review drawings.
09/24/24 – THP published roof safety review drawings, Rev. 1.
09/25/24 – Hamilton County, CMI and THP had a MS Teams meeting to review the roof safety drawings and proposed approaches.
09/26/24 – KBR completed main installation of Roof F.
10/25/24 – THP released initial safety package for pricing by KBR. THP working on platform design to finalize complete package.
10/31/24 – KBR completed Roof D,E, &F including initial punch work. Roof A,B, & C and punch trip review complete. All lightning protection work scheduled to start early November.
10/30/24- KBR completed the work on lower roofs A,B and C and THP completed the initial punch review with KBR and HC for these roofs. THP needs to review the final fibertite’s punch review for the final confirmation.
11/06/24- HP approved pay App No.4 from KBR and send it to HC for the final review
11/07/24- THP send out the Bulletin No.2 to KBR for Pricing.
11/15/24- THP had a visit to KBR’s warehouse to confirm the walk mat materials purchased by KBR.
12/03/24- KBR send the Pricing for Bulletin No.2 to THP for review.
12/05/24- THP requested the breakdown of cost and resubmitting the CO No.2 from KBR.
12/09/24- HP approved pay App No.5 from KBR and send it to HC for the final review.
12/10/24- KBR sent the breakdown of costs for CO#1 for THP’s review.
12/11/24 – THP forwarded breakdown of cost and backup review to Hamilton County.
12/18/24 – County and THP approved KBR pricing. Final change order to be coordinated with safety upgrade work.
01/29/25 – County sent KBR AIA Change Order No. 2 for signature.
01/30/25 – Project status – Roof installed. Change order No. 2 waiting for execution and weather to install new safety platforms, RTU removal, and roof reconfiguration.
02/04/25 – Change Order No. 2 executed.
03/06/25 – Lightning protection work is complete, KBR is still waiting on the certification letter from Maxwell.
03/21/25 – THP reviewed the shop drawings for the platform and sent it back with comments to KBR. KBR Believed it should be roughly 7-8 weeks from getting them on-site for install.
03/26/25 – THP/LJB’s proposal for roof in progress.
04/24/25 – LJB provided updated proposal on 4/17/25. THP sent final proposal to County for review.
05/21/25- KBR confirmed that fabrication for the ladder and platforms is completed and they are at their site ready for deliver and install. KBR are getting themselves put on the schedule and will follow up with THP once they have a date.
06/18/25 – KBR will begin roof work on 07/07, including installation of ladders, platforms, and fall arrest systems on the ladders. Remaining work includes installing walk mats, replacing drain rings and cages on all roofs, and capping abandoned curbs on Roof C. KBR anticipates completing the Change Order #2 (CO#2) work within approximately two weeks from the start date.
06/24/25 – KBR submitted the lightning protection certification for THP’s review.
07/11/25- KBR completed 90% of the CO#2 works including installing walk mat on roofs, platform installation on both roof C and E, installing drain ring & strainers and caping abounded curb.
07/30/25 – KBR will provide CO#3 and CO#4 for remaining work including safety railing on roof D and E, Hatch guard, stair tower rental and all the work regarding removing old davits and installing new fall protection system. (the fall protection system work will be based on LJB design)
HC Juvenile Justice Center Davit Upgrade (F027):
THP PM: Rycca Thacker, John Millar
03/27/25 – County identified a number of safety concerns with roof operations. THP and the County had follow up meetings.
04/17/25 – THP received proposal from LJB for design of the safety davit system.
04/18/25 – THP published SOSS for County review.
05/07/25 – SOSS approved.
05/29/25 – THP coordinating design with LJB. Initial design discussions/meetings complete and formal SD to be submitted mid-June.
06/23/25 – LJB sent the preliminary drawings for the fall arrest system upgrade to THP. The design will be discussed with HC on 06/26. If there are no major changes, the final design is expected to be completed by the end of July.
07/11/25 – LJB sent the 90% drawings set and it was approved by THP and HC. LJB planning to provide the final design by August first.
08/22/25 – KBR completed remaining work on the ladder at roof F.
08/27/25- THP requested an updated cost estimate from KBR for CO#4 with a labor and material breakdown on the few Items including ( Safety Railing Roof D and Roof E, Hatch Guard, Flash New Davits and New Fall Protection) per county’s request and deducting the Terrecon cost from the list since that will be through THP.
08/27/25 – LJB send final review documents to THP. THP to review then forward to the team.
09/10/25- Terracon conducted a site survey to inspect the platform and ladder on roofs. They have noted that (2) attachments bolts on the top of the ladder at Roof E were loose. THP has reached out to KBR regarding this matter, and they are planning to have the steel crew back on site to complete the work.
09/19/25- LJB adjusted few items in their drawings per THP request and THP has sent the final drawings to KBR and HC for their review. KBR is waiting on CO#4 approval to start the rest of the work.
09/26/25 – County requested a breakdown of CO #4 work to be completed with railing material costs provided by the County.
10/09/25 – KBR provided updated pricing for CO #4 with the County providing the railings.
10/10/25 – THP reviewed pricing and noted one item to update.
10/16/25 – KBR provided an updated CO #4 breakdown pricing.
10/16/25 – THP approved pricing.
10/20/25 – County sent fully executed CO #4 to all parties.
10/26/25 – County received pricing for railings for CO #4 work with KBR. THP to review once cut sheets and product information is provided.
12/10/25 – KBR had the crane on site for delivering the roof railing on Friday 12/5 and were planning to complete the work the week of 12/8 weather depending. The work will include the installation of the railing at the roof edge on roof D and E and railing around the hatch at roof D.
01/08/26 – The railing installation on both roof has been completed and installed safety railing at roof hatch needs to be replaced. KBR and LJB will begin the installation of the new fall arrest system at the beginning of march and all remaining work and miscellaneous items will be completed at that time. THP will schedule a meeting before starting the work on March to go over all items with KBR and LJB.
02/23/26: KBR has installed the new railing around the roof hatch and planning to start the work on March 2nd with LJB for installation new fall arrest system. The Crane will be on site on 03/2/26 and contractors are estimating the work will be completed by end of the March.
03/18/26: THP has reviewed the new design layout with LJB, KBR and HC and approved the layout for Roof E, and then the partial section of roof D on 3/20. The rest will be reviewed by THP on the first week of April.
04/30/26: Project summary – LJB and KBR have installed 95% of the fall arrest system. At roof D an assembly needed to be adjusted and fall arrest for the ladder system has a back ordered component. Contractor anticipates finishing end of May.
09/24/26 – Work reported to be complete. THP and KBR coordinating final punch review by Fibertite and Terracon.
10/07/26 – THP completed formal punch trip with KBR. Missing gates noted.
10/29/26 – KBR ordered gates.
2020 – Roof Replacement (F034) and Davit Upgrade (F027) Read More »