EMA – Tornado Sirens Arc Flash Study
PM = Matt/ Trades, Mike Barth
08/28/24 – ThermalTech submits SOSS for all sirens in Zone 4.
09/25/24 – TEI receives signed SOSS and PO for project. TEI to schedule kick off meeting with HCFD.
10/30/24 – TEI contacts Duke Energy for available fault at each location. TEI coordinates with HCFD for addresses of each siren. Model in Progress.
12/11/24 – Zone 4 sirens are modeled and the labels are ready for printing. TEI will print and deliver to HCFD.
01/29/25 – TEI to deliver the labels to HCFD.
02/26/25 – TEI delivers Arch Flash Labels for Zone 4 sirens.
03/26/25 – TEI delivers SOSS for zone 5 sirens. TEI receives PO to start the Zone 5 package.
04/23/25 – TEI to start the arc flash study for zone 5 sirens.
06/25/25 – No updates this month.
07/30/25 – DEG receives available fault from Duke for Zone 5 sirens and modelling is in process.
08/27/25 – Modeling of all sirens in progress.
10/29/25 – Modeling complete. Pending MCB and CMI review.
12/10/25 – No updates
01/28/26 – HamCo requests SOSS for next zone (assuming Zone 6).
02/25/26 – DEG submits SOSS for Zone 6.
03/25/26 – DEG receives PO and signed SOSS for Zone 6. DEG gathering data from duke and developing model. Zone 5 arc flash stickers to HamCo Trades.
04/29/26 – DEG completes modeling of zone 6 sirens. On Barth’s desk for review and approval, and then send to CMI for approval prior to printing labels for trades.
05/27/26 – No updates.
06/23/26 – DEG reviews model with CMI (Charlie) and gets CMI approval of model. DEG prints all zone 6 labels and delivers to Trades Electricians.
07/29/26 – Project deliverables complete until next years zone 1 SOSS approved.
EMA – Tornado Sirens Arc Flash Study Read More »