PM: Matt/Trades, Mike Barth
04/24/24 – TEI receives signed SOSS and PO.
05/29/24 – TEI develops Clifton (#81 W Nixon) drawings and submits plans to IBI for permitting. We will notify county trades once permit is approved.
06/26/24 – TEI secures permit for #81 West Nixon. HCFD to notify when the work is completed and ready for inspections.
07/24/24 – No updates this month.
08/28/24 – No new work this month.
09/25/24 – IBI inspection passes and EMA and Duke to connect power. Work on Siren #81 complete.
10/30/24 – No updates this month.
12/11/24 – Ben (EMA) sends Alex GPS coordinates for siren that needs to be permitted. TEI working on the permit documents.
01/29/25 – No Updates this month.
02/26/25 – No updates this month.
03/26/25 – No updates this month.
04/23/25 – Wes and Ben (EMA) coordinate location. Upon approval of location and connections by Duke, permit drawings will be issued.
05/28/25 – TEI finalizes permit drawings and submits to IBI for plan review.
06/25/25 – Plan review passed. Permit applied for on line. Ready to schedule work with trades.
07/30/25 – Permit was delivered to HCFD (Electricians). Inspection pending installation. DEG will call for inspection when notified that the siren has been installed by trades.
08/27/25 – IBI inspection occurred and passed on 08/27/25.
09/24/25 – No updates.
10/29/25 – No updates this month.
12/10/25 – No updates this month. Pending issues with existing poles. etc.
01/28/26 – No updates this month. Pending issues with existing poles. etc.
02/25/26 – No updates this month. Pending issues with existing poles. etc.
03/25/26 – No updates this month. Pending issues with existing poles. etc.
04/29/26 – No updates this month. Pending issues with existing poles. etc.
06/23/26 – No updates this month. Pending issues with existing poles. etc.
07/29/26 – No updates this month. Pending issues with existing poles. etc.
08/26/26 – EMA reaches out to Wes about possible relocation of pole in Wyoming (Chisholm Park).
09/23/26 – EMA and DEG are working on (2) siren locations for 2026, and (1) for 2027.
10/28/26 – (2) Sirens are in for QC review. Then will be issued for installation.