Hamilton County Facilities

Satellite Offices-A

Satellite Offices Archive

Animal Shelter – Due Diligence Study

10/28/19 – Champlin, THP, and ThermalTech meet on site at the Hamilton County SPCA for a building tour. We toured the facility to see existing conditions and meet with representatives from the ASPCA and SPCA to discuss requirements for animal shelters. TTE has the existing drawings for scanning.
12/11/19 – The teams revisited the project site last Friday, THP on Monday. We are creating the estimates and report scope this week in advance of turning over the final report and estimates.
12/12/19 – The team discussed what to put in the report for Bert and in current population and code population. This report is supposed to discuss if the County should renovate this space for the new code requirements for canine’s. The county is not actually responsible for the cat population. #1-Renovation Cost, #2-expand to code population needs, #3-New Renovation Cost? We are to send all summaries to Kru at Champlin. BW said he really needs this next week. BOCC terminated SCPA agreement this year and are now looking for keep SCPA services. Provide draft by 12/19 to County.
12/20/19 – All partners have submitted cost and write-ups to the County. The County is working with CA on new building cost estimates and any updates that might be associated with square foot cost. The Renovation/Upgrade of existing facility cost seemed to be within expected ranges.
12/13/19 – THP reviewed budget for reduced repair scope project and discussed with CA.
12/16/19 – THP had conference call with project team to discuss repair scope.
12/18/19 – THP finalized draft of building envelope assessment report and emailed to project team for review.
12/19/19 – THP finalized building envelope assessment report and issued to CA.
01/27/20 – All information submitted to the County in December, will check on any additional updates at this months meeting.
02/20/20 – No updates this month.
03/23/20 – No updates this month.
04/30/20 – No updates this month.
05/27/20 – No updates this month.
06/24/20 – No updates this month.
07/29/20 – Emailed Tony all the scanned drawings we have of the building.
08/26/20 – This project picked up a little bit this month in answering some building questions and discussing adding it to Archibus.
09/18/20 – New Arc Flash project SOSS sent to County, followed up with some additional drawings to Tony from study. This project can probably be archived.
09/24/20 – OK to Archive.

Animal Shelter – Due Diligence Study Read More »

Millvale – Lease Tenant Fit-Out

06/14/19 – IPM and TTE Met County onsite for kickoff field trip for lease space renovation.
06/21/19 – CHA, IPM and TTE put proposal together and submitted to County for consideration.
06/25/19 – Split proposal up into SD & Estimating and CD & Bidding for consideration.
06/27/19 – Submitted new SD & Estimating SOSS to Facilities for approval. Based on the findings in the SD phase we will update the DD, CD, Bidding & CA SOSS later if the project moves forward.
07/24/19 – SOSS approved. Four week time clock has started. TTE has visiting the site and taken off additional plumbing, HVAC and electrical. Bert gave us the contact to do additional fieldwork at the site. One additional plumbing drawing was found on site.
07/25/19 – County stated today that the all disciplines must have permittable style SD documents to attach as exhibits to the lease.
08/28/19 – The team completed the SD phase and cost estimate and submitted to the owner for review. The cost was higher than expected and a value engineering meeting was held with Facilities and JFS. We removed the HVAC from the project, removed one restroom, changed some of the finishes in the space. We then we updated the floor plans, furniture plans, HVAC, Electric and Plumbing and uploaded the new drawings to Archibus. Finally we updated the cost estimate to match the new scope. We are awaiting review and approval by owner.
09/24/19 – No updates. We are waiting on funding and approval to move to next phase.
10/09/19 – Master lease between CMHA and the city is approved. Project will move forward.
10/23/19 – DD set given to Hamilton County.
10/31/19 – Waiting on lease documents to City, waiting on approval to move forward on bidding.
11/01/19 – CD set scheduled to be given to Hamilton County. Bert gave us the background on using this space now and in the future. This may take some time to work this through the City process for DD drawings.
12/10/19 – CA attended walk through of Space with TTE, County, and Cincinnati to discuss scope of work.
01/30/20 – CHMA approved our proposed plan. The County needs this in writing so they can sublease this space and agree on amount of stay past end of lease. Bert said we are just getting through the administration stuff, the project is good to go in concept.
06/25/20 – Project on hold for now. RT will check on future feasibility.

Millvale – Lease Tenant Fit-Out Read More »