Hamilton County Facilities

P&D – Restroom Renovation

PM: John Nester, Terry Cannon
04/21/21 – Nester requested SOSS for small restroom renovation, emailed next day.
05/26/21 – Kickoff meeting scheduled Friday at 2:00 pm on site.
06/11/21 – Sent preliminary layout with new fixtures located.
06/18/21 – Sent owner review set to John & Greg for review.
06/21/21 – Answered budget questions & Small Project bidding questions via email.
06/25/21 – Use as many BOLD participants as we can.
04/28/21 – Prebid held last week. Addendum #1 issued this week. Addendum #2 will be issued Friday with some cost savings ideas included. Bids are due August 5.
08/16/21 – Bids received and tabulated and sent to County for approval.
08/20/21 – Post Bid review with DK went well. County, TEI and DK working through contract documents.
09/30/21 – PO and Contract approved, all paperwork sent to DK for processing, and project information requested.
10/28/21 – Paperwork received from DK. PO and Contract are in place and the project is ready to go.
12/08/21 – Pre-const mtg scheduled on site but rescheduled to next week for availability.
12/13/21 – Pre-Const mtg schedule for Wednesday.  Submittals are returned.  Permit drawings will be hand delivery to DK at meeting.
01/21/22 – Tumlin has measured for toilet partitions and Debra is updating the project schedule. Permits are ready for this job. DK arranging for temporary toilets. We just need to get started.
02/24/22 – DK almost done. Rough-in work complete and passed plumbing inspection. Walls are being reconstructed, partitions installed and fixture to be hung next.
03/31/22 – Tumlin performing change order work for extending toilet partitions this week. DK performing punchlist work this week. Change Order 1 approved.
04/28/22 – The project is complete. Punchlist was distributed and completed including change order work. Some minor touchup may still need to be done. We can start closing out this project.
05/25/22 – Working on closeout with DK at this time. No additional paperwork has been received yet. Bill says they are close.
06/17/22 – Spoke to Bill & Donna at DK. They are working on getting closeout documents.
07/27/22 – Most of the closeout documents have arrived. I think JN reached out for a PW document.
08/24/22 – Reached to DK for more closeout docs. PW received so far.
09/25/22 – All closeout documents received. Project ready to close out.