PM – Rycca, Mike Barth
09/25/24 – HamCo requests SOSS for Elevator Modernization project for (9) elevators in Courthouse. TEI and Elevar meet to discuss rolls on project. TEI and Elevar developing SOSS.
10/30/24 – Elevar provided SOSS to TEI.
10/30/24 – TEI submits SOSS for approval. Project pending SOSS approval and PO.
12/11/24 – TEI receives Signed SOSS and PO. TEI and JE perform initial walkthrough of all of the elevator machine rooms.
01/29/25 – TEI has design schedule. Field work ongoing.
02/25/25 – Elevar performed field work for all.
02/26/25 – TEI working on developing SD documents with a proposed end of March deadline for SD.
03/26/25 – Elevar provided SD drawings to TEI and SD meeting scheduled with HCFD.
04/24/25 – Team to meet with Court Admin/committee to review project, security, and finishes. Elevar has finish presentation prepared. HCFD to notify team when courts are available.
05/28/25 – Team waiting on HCFD to notify when courts committee are ready for review meeting.
06/25/25 – Team meets with Court Admins – get direction on security and finishes. TEI to submit updated schedule.
07/30/25 – Team sends proposed schedule with RFIs to HCFD for direction.
08/27/25 – Team meets with court admins and gets final sign off on selections. Team submits OPC for HCFD to obtain funding. Once funding approved, project will be sent to ITB.
09/24/25 – Project issuance pending funding approval.
10/30/25 – Project issuance pending funding approval.
12/11/25 – Project submission for 100% review on 12/15. ITB date in Jan 2026.
01/28/26 – Project out to bid. Prebid well attended. Bids due 2/26
02/26/26 – Bid opening today!
03/26/26 – Bids still under review by HC.
04/30/26 – Low bidder vetting meeting occurred. Contract in process with HC Purchasing. Notification of TKE buyout forwarded to HCFD.
05/27/26 – Triton contract approved at the BOCC meeting on 05/21/26. Preconstruction meetings to be scheduled early June.
06/23/26 – Preconstruction meeting conducted on the project with HCFD and court administrators. Contractor in the survey and submittal phase prior to ordering of equipment.
07/29/26 – Project in submittal development phase. Design team has not received submittals to date.
08/26/26 – Project in submittal development phase. Design team has not received submittals to date.
09/23/26 – Design team receives initial submittals.
10/28/26 – Submittals continue to get reviewed and returned. Mobilization anticipated approximately Mid-April 2027 (original schedule was mid-March 2027. The contract phase and procurement deposit caused the delay.