Hamilton County Facilities

CH – Facade Repairs/Roof Replacement (F005)

PM: Matt Butz, John Millar, Eryn Thamann
06/26/24 – THP provided SOSS to Elevar.
07/25/24 – County approved SOSS.
08/14/24 – THP and Elevar completed a kick off meeting and general walk of the roofs.
08/27/24 – SOSS approved. Kick off meeting held with HCFD, THP, Elevar. Building scanning schedule being coordinated for site access.
09/26/24 – Truscan came out two days ago and modeled the building. Elevar will share with the partners, over one billion points scanned, CH and surrounding areas. More fieldwork needed.
10/30/24 – Model shared with THP and SD continues.
12/09/24 – THP working with model and performing site work.
10/30/24 – Model shared with THP and SD continues.
12/11/24 – THP completed initial field work to confirm model accuracy. THP provided review comments and has begun working on model joints.
01/29/25 – THP has performed several facade tests but weather limited site work; surveying still ongoing to document stone/terra cotta joints. Roof plans are developed; THP/Elevar coordinating on roof edge details now.
02/25/25 – Deliverable schedule sent to MB. Work ongoing.
03/26/25 – Met with HCFD to review SD status drawings. THP has additional site investigation to perform but still look on track for May SD deliverable.
04/24/25 – Team is progressing with design. Elevar to get masonry contractor under contract to complete destructive investigation.
04/24/24 – THP field surveying work is wrapping up today (4/24). Any additional site visits will be on an as-needed basis for verifications. Background drawings complete and THP actively transferring field surveying data to drawing set, and tallying repair sizes/quantities.
05/28/25 – Decision on mason expected 05/29. Elevar to schedule work with HCFD.
06/26/25 – Mason under contract and patiently awaiting their onsite schedule. THP/Elevar meeting to coord. designs. Final SD set expected to HCFD end of July.
07/31/25 – Mason walk-thru 07/24 with THP/HCFD and scheduled onsite start for 08/04. Badging will start if crew will be inside but will determine at walk-thru. Deadline pushed back to accommodate mason.
08/28/25 – Waiting for final mason contractor to get badged to start investigative demo.
09/25/25 – Mason onsite in Sept and design team finalizing drawings based on findings.
10/30/25 – Final SD set provided to HCFD along with cost estimate. Review mtg schedule for 11/06 with HCFD/THP.
11/06/25 – THP and Elevar met with HC to review SD set. HC requested updates to OoPC and schedule.
11/21/25 – THP sent final OoPC to Elevar, with requested updates from HC.
12/01/25 – THP reviewed design schedule with Elevar and HC during 800 Broadway meeting.
12/11/25 – Final cost estimate and design schedule will be provided to HCFD this week.
01/29/26 – Elevar/THP working on SOSS.
02/23/26 – THP published fee proposal to Elevar for Phase II of design work.
03/26/26 – SOSS approval pending.
04/24/24 – THP update – THP field surveying work is wrapping up today (4/24). Any additional site visits will be on an as-needed basis for verifications. Background drawings complete and THP actively transferring field surveying data to drawing set, and tallying repair sizes/quantities.
04/30/26 – SOSS approved. Need to schedule kick-off meeting with team and HCFD.
05/28/26 – Design kickoff mtg occurred 05/27. Elevar to send pdf presentation to team for review with Court Admins. Team will provide design schedule very soon.
06/17/26 – Project placed on hold.
06/25/26 – On hold. Design kickoff minutes and presentation provided to HCFD.
07/30/26 – No update. Remains on hold.
08/14/26 – THP provided recommended critical repair scope and budget.
08/27/26 – Priority list provided by THP to HCFD. Could restart after November with very limited scope.
09/24/26 – Project on hold.
10/25/26 – Project on hold