Hamilton County Facilities

Courthouse

Courthouse

CH – B95 Office Suite Renovations

PM: Megan, Sam
10/30/25 – This project went out to bid this week. Sam will send out invites for prebid and bid opening.
12/11/25 – Triton is low bidder. Project in contract phase.
12/12/25 – Furniture and two drawer cabinets can be located close to the hot water radiators, they just have to be moved if we ever need to service the units.
01/28/26 – Contract goes in front of the board today. Bulletin #1 will go out next week with the changes requested from Rycca.
02/26/26 – Contract is signed. Triton is to pace projects out to place priority on Bondhill. Submittals and pre-mob items can begin.
03/26/26 – No update.
04/30/26 – Submittals are coming in. Project mobilization to be scheduled by County.
05/28/26 – Project tentative start on 8/10/26.
06/25/26 – No update.
07/30/26 – Submittals are being returned. Project start has adjusted to 8/31.
07/30/26 – RT said we may get new direction on final design for this space. We may need another Bulletin for this project.
08/28/26 – Mobilization on hold until scope changes are settled.
09/24/26 – Scope changes received. Bulletin is being prepared.
10/29/26 – Bulletin will be issued to Triton upon approval

CH – B95 Office Suite Renovations Read More »

CH – Parking Lot Repair (F029)

PM: Matt Butz, Paul Bellman
06/03/25 – County, Kleingers and THP had a meeting to discuss scope of asphalt repair work.
07/24/25 – County and THP met to discuss project phasing.
07/30/25 – THP published preliminary opinion of probable cost for the project.
08/08/25 – THP published SOSS.
08/18/25 – County had kick off meeting with Tumlin, Champlin, THP, and Kleingers.
08/20/25 – County approved SOSS.
08/28/25 – Kleingers scheduled to survey the parking lot.
09/08/25 – Kleingers survey received
09/22/25 – Kleingers, THP, HC reviewed Courtyard lot for RFI #03 regarding overlay vs milling.
11/05/25 – THP, HC, and Tumlin reviewed milling conditions and full depth repair options.
11/14/25 – Kleingers provided updated striping plan.
11/18/25 – THP reviewed new asphalt in courtyard during heavy rain. Puddling and improper slope was observed on east portion of lot.
01/28/26 – No updates – weather pending.
02/26/26 – No updates – weather pending.
03/24/26 – No updates – Status of ponding in Courtyard area?
04/30/26 – THP to review on site conditions.
05/28/26 – No updates. Work in adjacent areas ongoing.
06/25/26 – Sink hole and active line was discovered in Courtyard lot. THP, Davies, and HC discussed scoping, filling void, and providing cleanout per supplied detail. Tumlin to get CO cost to repair.
07/30/26 – No updates from THP. Have not heard from Tumlin on the CO costs to repair sink hole in Courtyard Lot.
09/23/26 – No updates.
10/29/26 – No updates. Punchlist coming and cleanout addressed soon.

CH – Parking Lot Repair (F029) Read More »

CH – Fire Door Repairs

PM: Sarah, Eryn
10/30/24 – SOSS in final review prior to sending.
12/09/24 – Pending approved PO.
01/29/25 – Pending approved PO.
02/25/25 – Pending approved PO.
03/26/25 – PO approved and Elevar will schedule walk-thru after first walk of 230.
04/24/25 – Walk-thru not scheduled yet.
05/28/25 – DD-level drawings are prepared. Elevar needs to review with Champlin/HCFD for general design intent; need bidding info.
06/26/25 – Ready for review with Champlin/HCFD.
07/31/25 – Ready for review with Champlin/HCFD.
08/28/25 – HC/Champlin/Elevar review meeting scheduled for 09/02 to review current sets and decide on bidding strategy.
09/25/25 – Finalizing cost estimates now. Drawings to be updated with any cost estimate comments. Specs to be completed after final project design review.
10/30/25 – Initial cost estimates complete and ready to review with HCFD. Need mtg scheduled to review estimates and what scope is base bid vs alternates. Also under review by separate hardware consultant.
12/11/25 – 95% review set provided to HCFD with costs. Elevar working on bid breakdowns now for the various buildings, alternates, and unit costs and will review with HCFD once complete.
01/29/26 – On Elevar’s current workload to write bid form breakdown.
02/26/26 – Elevar provided bid form breakdown. Rycca requested summary and Evan/Matt to setup meeting with Sheriff’s to review JC.
03/26/26 – Elevar to hold on design as-is. Evan/Matt to setup meeting with Sheriff’s to review JC in future. Work order in process for removing paint that may impact bid form.
04/30/26 – SOSSs approved for additional CA work. No update on whether paint removal from stickers was successful.
05/28/26 – No update. No update on whether paint removal from stickers was successful.
06/25/26 – No update.
07/30/26 – No update.
08/27/26 – No update.
09/24/26 – Awaiting paint removal status.
10/29/26 – No update.

CH – Fire Door Repairs Read More »

CH – Elevator Modernization

PM – Rycca, Mike Barth

09/25/24 – HamCo requests SOSS for Elevator Modernization project for (9) elevators in Courthouse. TEI and Elevar meet to discuss rolls on project. TEI and Elevar developing SOSS.
10/30/24 – Elevar provided SOSS to TEI.
10/30/24 – TEI submits SOSS for approval. Project pending SOSS approval and PO.
12/11/24 – TEI receives Signed SOSS and PO. TEI and JE perform initial walkthrough of all of the elevator machine rooms.
01/29/25 – TEI has design schedule. Field work ongoing.
02/25/25 – Elevar performed field work for all.
02/26/25 – TEI working on developing SD documents with a proposed end of March deadline for SD.
03/26/25 – Elevar provided SD drawings to TEI and SD meeting scheduled with HCFD.
04/24/25 – Team to meet with Court Admin/committee to review project, security, and finishes. Elevar has finish presentation prepared. HCFD to notify team when courts are available.
05/28/25 – Team waiting on HCFD to notify when courts committee are ready for review meeting.
06/25/25 – Team meets with Court Admins – get direction on security and finishes. TEI to submit updated schedule.
07/30/25 – Team sends proposed schedule with RFIs to HCFD for direction.
08/27/25 – Team meets with court admins and gets final sign off on selections. Team submits OPC for HCFD to obtain funding. Once funding approved, project will be sent to ITB.
09/24/25 – Project issuance pending funding approval.
10/30/25 – Project issuance pending funding approval.
12/11/25 – Project submission for 100% review on 12/15. ITB date in Jan 2026.
01/28/26 – Project out to bid. Prebid well attended. Bids due 2/26
02/26/26 – Bid opening today!
03/26/26 – Bids still under review by HC.
04/30/26 – Low bidder vetting meeting occurred. Contract in process with HC Purchasing. Notification of TKE buyout forwarded to HCFD.
05/27/26 – Triton contract approved at the BOCC meeting on 05/21/26. Preconstruction meetings to be scheduled early June.
06/23/26 – Preconstruction meeting conducted on the project with HCFD and court administrators. Contractor in the survey and submittal phase prior to ordering of equipment.
07/29/26 – Project in submittal development phase. Design team has not received submittals to date.
08/26/26 – Project in submittal development phase. Design team has not received submittals to date.
09/23/26 – Design team receives initial submittals.
10/28/26 – Submittals continue to get reviewed and returned. Mobilization anticipated approximately Mid-April 2027 (original schedule was mid-March 2027. The contract phase and procurement deposit caused the delay.

CH – Elevator Modernization Read More »

CH – Facade Repairs/Roof Replacement (F005)

PM: Matt Butz, John Millar, Eryn Thamann
06/26/24 – THP provided SOSS to Elevar.
07/25/24 – County approved SOSS.
08/14/24 – THP and Elevar completed a kick off meeting and general walk of the roofs.
08/27/24 – SOSS approved. Kick off meeting held with HCFD, THP, Elevar. Building scanning schedule being coordinated for site access.
09/26/24 – Truscan came out two days ago and modeled the building. Elevar will share with the partners, over one billion points scanned, CH and surrounding areas. More fieldwork needed.
10/30/24 – Model shared with THP and SD continues.
12/09/24 – THP working with model and performing site work.
10/30/24 – Model shared with THP and SD continues.
12/11/24 – THP completed initial field work to confirm model accuracy. THP provided review comments and has begun working on model joints.
01/29/25 – THP has performed several facade tests but weather limited site work; surveying still ongoing to document stone/terra cotta joints. Roof plans are developed; THP/Elevar coordinating on roof edge details now.
02/25/25 – Deliverable schedule sent to MB. Work ongoing.
03/26/25 – Met with HCFD to review SD status drawings. THP has additional site investigation to perform but still look on track for May SD deliverable.
04/24/25 – Team is progressing with design. Elevar to get masonry contractor under contract to complete destructive investigation.
04/24/24 – THP field surveying work is wrapping up today (4/24). Any additional site visits will be on an as-needed basis for verifications. Background drawings complete and THP actively transferring field surveying data to drawing set, and tallying repair sizes/quantities.
05/28/25 – Decision on mason expected 05/29. Elevar to schedule work with HCFD.
06/26/25 – Mason under contract and patiently awaiting their onsite schedule. THP/Elevar meeting to coord. designs. Final SD set expected to HCFD end of July.
07/31/25 – Mason walk-thru 07/24 with THP/HCFD and scheduled onsite start for 08/04. Badging will start if crew will be inside but will determine at walk-thru. Deadline pushed back to accommodate mason.
08/28/25 – Waiting for final mason contractor to get badged to start investigative demo.
09/25/25 – Mason onsite in Sept and design team finalizing drawings based on findings.
10/30/25 – Final SD set provided to HCFD along with cost estimate. Review mtg schedule for 11/06 with HCFD/THP.
11/06/25 – THP and Elevar met with HC to review SD set. HC requested updates to OoPC and schedule.
11/21/25 – THP sent final OoPC to Elevar, with requested updates from HC.
12/01/25 – THP reviewed design schedule with Elevar and HC during 800 Broadway meeting.
12/11/25 – Final cost estimate and design schedule will be provided to HCFD this week.
01/29/26 – Elevar/THP working on SOSS.
02/23/26 – THP published fee proposal to Elevar for Phase II of design work.
03/26/26 – SOSS approval pending.
04/24/24 – THP update – THP field surveying work is wrapping up today (4/24). Any additional site visits will be on an as-needed basis for verifications. Background drawings complete and THP actively transferring field surveying data to drawing set, and tallying repair sizes/quantities.
04/30/26 – SOSS approved. Need to schedule kick-off meeting with team and HCFD.
05/28/26 – Design kickoff mtg occurred 05/27. Elevar to send pdf presentation to team for review with Court Admins. Team will provide design schedule very soon.
06/17/26 – Project placed on hold.
06/25/26 – On hold. Design kickoff minutes and presentation provided to HCFD.
07/30/26 – No update. Remains on hold.
08/14/26 – THP provided recommended critical repair scope and budget.
08/27/26 – Priority list provided by THP to HCFD. Could restart after November with very limited scope.
09/24/26 – Project on hold.
10/25/26 – Project on hold

CH – Facade Repairs/Roof Replacement (F005) Read More »

CH – 6th Floor Sheriff’s Storage

PM: Eryn Thamann, Matt Butz
08/27/24 – Elevar SOSS approved. TEI to submit SOSS.
09/24/24 – TEI submitted SOSS to HCFD. Elevar requested design kick off meeting with HCFD.
10/30/24 – Drawings are setup and design team need to walk space for FV and finish discussions.
12/09/24 – Need to review finishes with HCFD. Will perform site work 12/12. BW said bring over finishes and he would like to maybe replaced tile in main hallways.
01/02/25 – TEI reached out for update on project progress.
01/27/25 – Kickoff meeting occurred 1/22, SD & Cost Due to John Nester 3-4 weeks after meeting.
02/26/25 – Elevar to gather full SD set for HCFD submission. Archibus project made and SD estimates can be added. ThermalTech will complete SD drawings by Friday 2/28.
02/27/25 – JN will bring in Sheriff Office for final review early March for this job.
03/26/25 – Team met with stakeholders to review SD options. Elevar will provide another round of SD options and storage options based on new info from meeting.
04/24/25 – Elevar provided second round of SD plan options and Sheriff storage options for selection. Upon plan and storage selections, the team can procced with design docs.
05/28/25 – No update.
06/26/25 – Elevar to update Archibus cost estimates.
07/31/25 – Elevar to update Archibus cost estimates.
08/28/25 – Estimates updated and new options uploaded.
09/25/25 – No update.
10/30/25 – No update.
12/11/25 – No update.
01/29/26 – Elevar to submit SOSS. Need final decision on Sheriff’s storage options or no storage included. Confirm no separate interior office for Sheriff’s IT group.
02/26/26 – Elevar has remaining fee and will start on this immediately.
03/26/26 – DEG to finalize MEP drawings and a final HCFD review set will be ready.
04/30/26 – Set is 95% and on hold for final bidding info.
05/28/26 – Need to prep documents for trades work. Elevar to submit building permit and DEG to submit IBI permit.
06/25/26 – Elevar to submit building permit and DEG to submit IBI permit this week.
07/30/26 – Kickoff meeting held 07/22. IBI permit approved. Building permit still under review.
08/27/26 – Kickoff meeting held with trades. IBI review approved and DEG will submit. Building permit paid for and wall bracing engineering change submitted.
09/24/26 – Will postpone construction start until approx. Nov 2026.
10/29/26 – Restart?

CH – 6th Floor Sheriff’s Storage Read More »

CH – Parking Lot Security

PM: Matt Butz, Sam Hoffman, Mike Barth
04/25/24 – Champlin has submitted SOSS, ThermalTech submitted SOSS recently.
05/30/24 – SOSS returned. Project kickoff to be scheduled in near future. BW said that this project on the fast track due to a recent incident in the parking lot.06/27/24 – Kickoff to be scheduled.
07/25/24 – Meeting held on site with County, Champlin, and several judges. Champlin is investigating fencing options and guard booth options for review. Plan will be modified based on comments in the field.
08/12/24 – THP completed a cursory field measurements for review of the proposed fencing.
08/12/24 – THP sent proposal to Champlin for review.
08/27/24 – THP sent SOSS to County for review.
08/29/24 – THP working on design with Champlin.
08/29/24 – Second meeting held for more investigation. THP found that additional structure will be needed for fence and guard booth.
09/25/24 – THP issued bid documents 9/20/24.
10/31/24 – Project is out to bid. Opening on 11/8.
01/30/25 – Tumlin was awarded the bid. Kickoff held. Permit submitted 1/29. Pending zoning and historical society approval. Submittals incoming.
02/27/25 – Submittals in progress. Tentative schedule received. Rejection received from the historical society.
03/27/25 – Submittals in progress. Zoning hearing scheduled for 4/2 for historical variance.
04/24/25 – Historical approval provided given some aesthetic changes to the project. Tumlin to provide pricing on the changes.
05/29/25 – Working with guard booth manufacturer to meet energy code requirements.
06/20/25 – THP submitted Bulletin #1. This covers the revisions that resulted from historic review board comments.
06/25/25 – THP received preliminary pricing from KT Holden for resurfacing lots: 250k.
07/31/25 – County approved moving forward with the Resurfacing project.
08/26/25 – THP modified the footing design to accommodate a continues concrete curb. THP preparing final sketch to be published on 8/30 with Bulletin No. 4.
09/24/25 – THP issued bulletin #4 on 8/29/25 to add grade beam for field conditions and new parking lot resurfacing work. Project in CA
10/30/25 – Grade beams installation onging. Guard booth will be lowered into place this weekend. Progress continues.
01/28/26 – Steel for door installed. Work ongoing.
02/26/26 – Cold formed steel going up in the next couple weeks. Fence material delivered. Phase 2 is pushed back slightly to align work.
03/26/26 – Phase 1 nearly complete. Cladding structure to begin weather dependent. Phase 1 fence installed. Phase 2 tentative date is 4/13.
04/30/26 – Phase 1 complete this week. Following for punch and commissioning. Phase 2 to begin 5/11. Parking on e court street and bus stop coordinated with city to prep for phase 2. Rycca, Mike and Derrick met onsite for security plants. SOSS incoming.
05/28/26 – SOSS for security plant beds submitted. Sheriffs have solved their booth connection issue and kicked off phase 2.
06/25/26 – Phase 2 to switch over mid July. Doors and booth to be tested to ensure seamless transition.
07/30/26 – Phase 2 has begun. Demo exposed some underground conditions that are being resolved. Phase 1 issues have been worked out, including new controls after being struck by lightning.
08/28/26 – Issues discovered below grade have been solved. Grade beams almost complete. Steel has been erected.
10/29/26 – Finishing fence this week. Programming second door. Ready for turn over next week.

CH – Parking Lot Security Read More »

CH – North and South Riot Door Refurbishment

PM: Matt Butz, Sam Hofmann
04/25/24 – SOSS returned. Project to be scheduled in.
05/30/24 – Project to start once first phase is complete.
06/27/24 – Field verification completed. Drawings in progress.
07/25/24 – No Update.
08/29/24 – Owner review submitted. Investigating one more option for interior vestibule doors. Project will be ready to bid in next couple of weeks.
09/26/24 – Project will go out to bid next week.
10/31/24 – Project is out to bid. Bid opening is 11/8.
12/12/24 – No bids received. Project was put back out to bid and opens on 12/19. Olek intends on bidding.
01/30/25 – Olek was awarded the bid. Contract is still in progress. Kickoff to be scheduled in near future. Permit to be submitted in near future.
02/27/25 – Contract in progress.
03/27/25 – Kickoff held. Submittals in progress.
04/24/25 – Doors have been removed and refurbishment is in progress.
05/29/25 – No Update.
06/26/25 – No Update.
07/31/25 – Call to discuss potential additional scope scheduled. Doors still in progress.
08/28/25 – Olek to reinstall riot doors in mid september. Electrical work to be complete during this visit. Any items that need to be taken to their shop will be removed and brought back after refurbishment.
09/25/25 – Olek currently onsite prepping for installtion of riot doors and interior doors.
10/30/25 – Door hardware supply issues pushed installation of riot doors back.
12/11/25 – Olek has been back on site. Ran into issues with the thresholds and pivots. Olek will be back mid january to continue work.
01/28/26 – Olek did not come back on site as first promised. Olek not responsive or timely. Champlin gave them a notice to be on site 1/19 or they would be referred to the prosecuter. Olek agreed they were in breach of contract but would not be on site until 1/26. The snow storm pushed that visit back until acceptable weather. County to provide prosecuter with letter.
02/26/26 – Olek to be back on site on March 9th to complete all remaining work.
04/30/26 – All work is complete. Closeouts are nearing completion.
05/28/26 – Closeouts outstanding. DK to complete a couple punch items.
06/25/26 – Close outs reviewed and several items still needed.
07/30/26 – Final punch item to be complete by Olek in August.
08/28/26 – Olek on site to complete punch work.
09/24/26 – Punch work complete. Olek sent official request for multiple change orders. Champlin has recommended denying request.
10/29/26 – Olek sent official request citing the contract. Champlin to provide official response.

CH – North and South Riot Door Refurbishment Read More »

CH – Common Pleas AV Upgrades

PM: Megan, Mike Barth, Mike Murphy
04/24/24 – TEI receives signed SOSS and PO.
5/29/24 – HCFD, TEI and Judge Jenkins Visits Montgomery County CH to see system in action.  Champlin and TEI visit all courtrooms to develop plans and take measurements of existing benches for install locations of equipment.
06/26/24 – Weekly meetings are conducted every Wednesday afternoon.   The most current EV equipment has been sent from BIS to the team.  TEI has Design documents well developed and will be conducting a final walk thru of each of the courtrooms on 06/27/24 as soon as the docket clears.
07/24/24 – TEI will provide HCFD a final review set on 7/26/24. HCFD will review and get comments back to TEI by 8/2/24. Project to be issued for bidding on 8/7/24.
08/28/24 – Project has been issued for bidding. Prebid meeting was held on 08/23 – (2) bidders attended. Bid opening scheduled for 09/19.
09/25/24 – Received (1) bid from DK, (39% over budget). Rejected the bid, repackaged and re-issued for REBID. Rebid Prebid meeting scheduled for 10/18 and Bid opening on 11/06. TEI reaching out to area ECs by phone and notifying of bid opportunity.
10/30/24 – Final addendum issued on 10/30/24. Bid Opening 11/06/24 at 11:00 AM.
12/11/24 – Bids open. DK low bid. TEI vets the DK bid and sends letter or recommendation to HCFD. project pre-const meeting to occur upon contract approval.
01/29/25 – DK, HCMC, HCFD, BIS and TEI are in the pre-construction/procurement phase of the project. DK to provide project schedule.
02/26/25 – DK, HCFD, BIS, TEI and HCCPC have weekly meeting to update status and tracking.
03/26/25 – Work on CR 580 has started. Next CR’s were discussed at the meeting this week. BIS to ship the next 2 rooms equipment week of 4/10.
04/23/25 – Work continues in CR 580. End of this week DK to be ready for carpet install (HCFD covering carpet install). Floor slab xray scheduled for 04/26/25 (Saturday).
05/28/25 – BIS sends technician to CR 580 today for coordination with DK. All DK field issues/concerns addressed. Field visit to fire up the system on 05/30 at 1:00 PM.
06/25/25 – CR 580 complete, pending training on equipment and demo to other Judges.
07/30/25 – CR 580 training completed. CR 580 in use and DK is now working on CR 320. Tweaks are happening as the systems are being placed into service. Rycca asked if we should order the AV equipment and set it back in the Archive room and they can use them out of the boxes on the sixth floor. Punchlist scheduled for 8/5 at 3PM.
08/27/25 – Punchlist for room 580 completed. DEG issues the Punchlist to DK. Installation of BIS equipment installed this week.
09/24/25 – Finalizing CR320. Moving on to CR 380 next. At const meeting, it was discussed to ship all equipment as soon as ample storage space for 16 more rooms equipment. Arpa funds must all be spent by 12/31/2026.
10/29/25 – Programming installed in Room 320. Work starting in rooms 300 and 380.
12/10/25 – Work continues with CR 300 and 380. Punchlist scheduled for 12/10/25 cancelled due to court session running long.
01/28/26 – Project continues.at the meeting today discussed the next 2 rooms to be worked on (340 and 360). This will finish the CRs on the 3rd floor.
02/25/26 – Project continues. Work on 3rd floor progressing. Speakers swapped out in 580 and sound quality substantially improved. DK brings in “sound expert”, Leo Little form ICS, to evaluate rooms. Leo to provide quotation to DEG for sound engineering services.
03/25/26 – Electrician changes necessitated for the project. DK to update situation ASAP. finishing CR 330 and moving to 360 and 340 next.
04/29/26 – Work continues in Rooms 340 and 360. Walk for 485 and 496 scheduled for 5/5.
05/27/26 – work continues in room 340 and 360. Rooms 485 and 495 are next (waiting on floor boxes to be fabricated). Walking locations on the 5th floor 05/27/26.
06/23/26 – Sound Guy (Leo Little) models room 485 and returns proposed layout with the speakers that were purchased from BIS.
07/29/26 – Sound guy visits room 300, modelling the room. HC directs Leo to only use the bill of materials for the rooms, and to not give recommendations for improved sound quality with equipment not in the original BOM.
08/26/26 – Room 300 sound recommendations installed. Sound quality greatly improved. ICS states that next 2 rooms are scheduled to be sent today.
09/23/26 – Work continues on the installation. ICS completes all room sound models and recommendations. There are 2 rooms (320 and 380) that HCFD sent comments back to ICS for tweaks.
10/28/26 – All sound models received on all rooms. Punchlist walk occurred on 10/26/2026. Work starting on Jenkins CR on Monday 11/02.

CH – Common Pleas AV Upgrades Read More »

CH – Law Library Text Room Renovation

PM – Jesse Estes, Sam Hofmann, Terry Cannon
12/07/23 – Signed SOSS received. Kickoff meeting requested.
01/22/24 – Load calculations are complete, fieldwork is started and mostly complete. Initial findings for AHU and HVAC needs sent to project team. In subsequent discussions it was decide to upgrade the unit for what we need in this space and do not try to “make” existing unit work if its undersized. TTE will design with that in mind.
01/31/24 – Review drawings to be ready in two weeks. TE to finish MEP review for that issuance.
02/29/24 – Final review meeting ready to be scheduled.
03/28/24 – Review meeting to be scheduled for first week of April.
04/25/24 – Review meeting held. Notes from Library received and changes have been made. They need to approve budget.
06/27/24 – Budget is still being worked out. Mothers room to be listed as an alternate. CDs in progress. Pull Mother’s Room out as an alternate. Laura got more money but not all of it. RR Alternate #1, Mother’s Room Alternate #2.
07/25/24 – No Update.
08/29/24 – Voting on new budget today and it should go forward soon.
09/26/24 – Budget was approved. Project to continue in October.
10/31/24 – Project goes out to bid today.
12/12/24 – Bid opens today.
01/30/25 – Alpha was awarded the bid. Contract still in progress. Kickoff to be scheduled in near future. Permit to be submitted in near future.
02/27/25 – Contract in progress.
03/27/25 – Kickoff scheduled for 4/2. Submittals incoming.
04/24/25 – Submittals in progress.
05/29/25 – Pre-mobilization meeting held. Alpha to provide schedule.
06/26/25 – Demo in progress. Freight elevator is down and has stopped work. RTU submittals were returned and we are working on an electrical requirements on the submittal with the vendors now. We have had several meetings trying to lock this down. Lead times range from 6 to 10 weeks.
07/31/25 – Demo is complete. Abatement of flooring to begin this week. Alpha to submit PCO related to plaster repair. AHU submittals have been received and approved with a new manufacturer. It took a long time to get there and there may be a credit to the project when all is said and done (Carrier/CaptivAire to York).
08/28/25 – Abatement will begin 9/2. Work paused during abatement delay. County is requesting more funds for plaster repair CO. Alpha was released to work up to cost of deduct from flooring removal.
09/25/25 – Framing has begun. Bathrooms to be turned over by end of October.
10/30/25 – Bathrooms to be turned over before 11/4. Asbestos concern to be investigated by the county. Work continues.
12/11/25 – Abatement of above ceiling pipe is complete. Alpha to remobilize and continue work.
01/28/26 – Bathroom back punch complete. Several items outstanding. Mid february completion.
02/26/26 – Library punch complete. Punch work outstanding.
03/26/26 – Back punch complete and work verified. Waiting on closeouts.
04/30/26 – Minor additional backpunch items sent to Alpha. Waiting on closeouts.
05/28/26 – No update.
06/25/26 – Closeouts outstanding. Shelf collapsed and new pins are being installed.
07/30/26 – No Update.
08/28/26 – Trades to fix all shelves. Alpha to come fix damaged shelves and adjust doors.
09/24/26 – Alpha to fix damaged shelves and conceal fasteners. Dehumidifier running to remedy door issues.
10/29/26 – Alpha to fix shelves and plaster in conference room.

CH – Law Library Text Room Renovation Read More »