Hamilton County Facilities

CH/JC/TPC/800 – Panic Button System Upgrade

PM – Matt Butz, Mike Barth

07/28/21 – Thermal authors and submits SOSS. TEI receives signed SOSS and PO from Hamilton County. TEI and HCFD to schedule design kick off meeting first week or two of August.

08/26/21 – HCFD PM and TEI schedule field work at all (4) buildings the afternoon of 09/02/21. TEI has coordinated with SecureTech and project is progressing.

10/26/21 – Project in contract phase. Construction to be completed once contract/PO is BOCC approved.

12/13/21 – Contracts sent to SecureTech.  Pre-install training meeting with HCSO conducted last week.  Parts are ordered and the will be available early January 2022.  Install Scheduled to occur beginning MLK weekend 2022.

01/25/22 – Installation was completed on the weekend of 01/17/22.  Securetech is working on getting closeout information to submit.  TEI and HCFD to provide punchlist the beginning of February.

02/23/22 – All close out documents complete.   Final pay application received.   HCFD to provide TEI with mark ups of button locations to show on CAD drawings.   Upon completion of the as-built conditions, project will be archived.

04/27/22 – TEI receives the mark ups for the CH for As-built documents 04/21/22.  Upon completion of the as-builts (drawings complete, MCB to review final drawings), O&M manuals will be delivered to project can be closed out.

05/26/22 – TEI to provide HCFD with (2) full size sets to deliver to HCSO.   Project complete upon turn over of full size drawings.

06/28/22 – Project complete.

07/27/22 – TEI Delivers thumb drive with electronic version of the drawings per HCSO request to Matt Butz.