PM – Matt Butz, Mike Barth
07/28/21 – Thermal authors and submits SOSS. TEI receives signed SOSS and PO from Hamilton County. TEI and HCFD to schedule design kick off meeting first week or two of August.
08/26/21 – HCFD PM and TEI schedule field work at all (4) buildings the afternoon of 09/02/21. TEI has coordinated with SecureTech and project is progressing.
10/26/21 – Project in contract phase. Construction to be completed once contract/PO is BOCC approved.
12/13/21 – Contracts sent to SecureTech. Pre-install training meeting with HCSO conducted last week. Parts are ordered and the will be available early January 2022. Install Scheduled to occur beginning MLK weekend 2022.
01/25/22 – Installation was completed on the weekend of 01/17/22. Securetech is working on getting closeout information to submit. TEI and HCFD to provide punchlist the beginning of February.
02/23/22 – All close out documents complete. Final pay application received. HCFD to provide TEI with mark ups of button locations to show on CAD drawings. Upon completion of the as-built conditions, project will be archived.
04/27/22 – TEI receives the mark ups for the CH for As-built documents 04/21/22. Upon completion of the as-builts (drawings complete, MCB to review final drawings), O&M manuals will be delivered to project can be closed out.
05/26/22 – TEI to provide HCFD with (2) full size sets to deliver to HCSO. Project complete upon turn over of full size drawings.
06/28/22 – Project complete.
07/27/22 – TEI Delivers thumb drive with electronic version of the drawings per HCSO request to Matt Butz.