PM – Matt Butz, Mike Barth
7/27/21 – TEI authors and submits SOSS. TEI receives signed SOSS and PO from HCFD. Design kick off meeting to be scheduled early August.
08/26/21 – Field work, pre construction meeting scheduled with DK at 1:30 PM on 08/26/21. Construction to commence thereafter.
10/26/21 – Project in construction. Issues with installation in process of developing repair plan.
12/13/21 – Project complete with the exception of wall path and painting. O&M manuals delivered to HCFD.
01/25/22 – Project complete pending receipt of closeout documents from DK.