PM: Megan, Sam Hofmann
04/25/24 – SOSS returned. Project to be scheduled in.
05/30/24 – Initial field verification complete. We will need a second trip to take dimensions.
06/27/24 – Second trip complete. CDs in progress.
07/25/24 – No Update.
08/29/24 – Owner review set submitted. Project will be issued for bid in next couple of weeks.
09/26/24 – Project out to bid. Pre-bid scheduled for 9/30. ITB sent to multiple stained glass vendors.
10/31/24 – Bids received. One vendor had a bond issue, one bidder did not fill out XBE paperwork properly. Purchasing to provide direction.
12/12/24 – Project is in contract phase.
01/30/25 – Contract is still in progress. Kickoff to be scheduled in near future.
02/27/25 – Contract Finalized. Kickoff to be scheduled.
03/27/25 – Kickoff held. Submittals incoming.
04/24/25 – Submittals in progress.
05/29/25 – Phase 1 windows are removed and taken back to the shop for refurbishment.
06/26/25 – Progress meeting at the shop scheduled for mid July.
07/31/25 – Windows still in progress.
08/28/25 – Phase 1 windows to be reinstalled in september. Phase 2 windows will be removed during the same time. Tentive completion date of end of october.
09/25/25 – Reinstallation of phase 1 began this week. Removal of phase 2 in progress.
10/30/25 – All storm windows have been installed. Stain glass installation of phase 1 to begin shortly. Phase 2 to be complete by end of november. County to request change order related to the plaster repair at window jambs.
12/11/25 – One section of stained glass installed. Second half of windows are still under repair. Background checks for installers have been over 90 days. County allowed stain glass to be reinstalled all at once when phase 2 windows are ready.
01/28/26 – No update.
02/26/26 – No update.
03/26/26 – Breilmeyer to mobilize this week. Installing half of glass and taking the other half to their shop.
04/30/26 – Half of stained glass is installed. Tentative completion at end of may.
05/28/26 – Breilmeyer to mobilize 6/8 to install the second half of the glass.
06/25/26 – Second half install ongoing.
08/28/26 – Installation complete. 1 punch item outstanding.
09/24/26 – No Update.
10/29/26 – Punch item complete. closeouts outstanding