PM: John Nester, Sam Hofmann
04/25/24 – SOSS returned. Project to be scheduled in. We need the PO by mid-November and the project must be complete by 11/1/25, they are moving out of the lease space.
05/30/24 – Kickoff held with Thermaltech, County, Reentry and Champlin. Some minor redesign will be explored.
06/27/24 – New options will be provided to Trina this week.
07/25/24 – New options presented. Final plan confirmed. CDs in progress. Owner review scheduled for 8/14.
08/29/24 – Final owner review meeting held. Project will be issued for bid in next couple of weeks.
09/26/24 – Project out to bid. Pre-bid scheduled for 9/30.
10/31/24 – Triton is low bidder. Bid vet to be scheduled in near future.
12/12/24 – Project is in contract phase.
01/30/25 – Contract still in process. Kickoff to be scheduled in near future. Permit to be submitted in near future.
02/27/25 – Contract finalized. Kick off to be scheduled.
03/27/25 – Kickoff held. Submittals incoming.
04/24/25 – Submittals in progress.
05/29/25 – Submittals in progress. Kickoff meeting scheduled for next Wednesday.
06/26/25 – Demo for Phase 1 in progress.
07/31/25 – Demo complete for Phase 1. Re-entry to move to 4th floor space to give Triton full access to project area.
08/28/25 – Phase 2 demo is complete. Triton met with County and Champlin to discuss change orders. Adjusted COs provided. HC reported today that they would like to Triton to be completed in October 2025.
09/25/25 – Project on schedule to finish end of October. All change orders settled. Work continues.
10/30/25 – Project nearing completion. Furniture delivered to site. Triton will most likely get TCO approval early next week. Fire sprinklers are being added in a couple of pockets. We are keeping the window washing sprinklers heads as-is but Preferred will have to update their permit drawings after the TCO is approved.
12/11/25 – Fire protection work took longer than expected. Inspection to be scheduled for next week. Final CO expected before Christmas.
01/28/26 – Inspector will not provide CO until the exterior stair door is fixed. Trades is fixing the door starting on 2/2. Bulletin 2 for window shades and power issued and waiting pricing.
02/26/26 – Bulletin 1 pricing received. Work outstanding.
03/26/26 – Bulletin #2 pricing has been received and approved. Triton to begin electrical work.
04/30/26 – Blinds installation outstanding. All other work complete.
05/28/26 – Closeouts received and returned. Triton to submit outstanding items.
06/25/26 – No update.
07/30/26 – Hardcopies to be delivered to County.
08/28/26 – Hardcopies delivered. Access control programming complete.
10/29/26 – No update.