PM: Matt Butz, Sam Hofmann
04/25/24 – SOSS returned. Project to be scheduled in.
05/30/24 – Project to start once first phase is complete.
06/27/24 – Field verification completed. Drawings in progress.
07/25/24 – No Update.
08/29/24 – Owner review submitted. Investigating one more option for interior vestibule doors. Project will be ready to bid in next couple of weeks.
09/26/24 – Project will go out to bid next week.
10/31/24 – Project is out to bid. Bid opening is 11/8.
12/12/24 – No bids received. Project was put back out to bid and opens on 12/19. Olek intends on bidding.
01/30/25 – Olek was awarded the bid. Contract is still in progress. Kickoff to be scheduled in near future. Permit to be submitted in near future.
02/27/25 – Contract in progress.
03/27/25 – Kickoff held. Submittals in progress.
04/24/25 – Doors have been removed and refurbishment is in progress.
05/29/25 – No Update.
06/26/25 – No Update.
07/31/25 – Call to discuss potential additional scope scheduled. Doors still in progress.
08/28/25 – Olek to reinstall riot doors in mid september. Electrical work to be complete during this visit. Any items that need to be taken to their shop will be removed and brought back after refurbishment.
09/25/25 – Olek currently onsite prepping for installtion of riot doors and interior doors.
10/30/25 – Door hardware supply issues pushed installation of riot doors back.
12/11/25 – Olek has been back on site. Ran into issues with the thresholds and pivots. Olek will be back mid january to continue work.
01/28/26 – Olek did not come back on site as first promised. Olek not responsive or timely. Champlin gave them a notice to be on site 1/19 or they would be referred to the prosecuter. Olek agreed they were in breach of contract but would not be on site until 1/26. The snow storm pushed that visit back until acceptable weather. County to provide prosecuter with letter.
02/26/26 – Olek to be back on site on March 9th to complete all remaining work.
04/30/26 – All work is complete. Closeouts are nearing completion.
05/28/26 – Closeouts outstanding. DK to complete a couple punch items.
06/25/26 – Close outs reviewed and several items still needed.
07/30/26 – Final punch item to be complete by Olek in August.
08/28/26 – Olek on site to complete punch work.
09/24/26 – Punch work complete. Olek sent official request for multiple change orders. Champlin has recommended denying request.
10/29/26 – Olek sent official request citing the contract. Champlin to provide official response.