JC – Pneumatic Delivery System

09/03/20 – SOSS and scope of work discussed for this project.
09/22/20 – Initial fieldwork.
09/23/20 – Pulled drawings from the Archive and scanned them for use on this job.
10/27/20 – Talked to Colombo and got a quote for system replacement, shared cost with county.
12/15/20 – Very preliminary cost and options sent to county and sheriff for review.
12/30/20 – Email summary sent to county and sheriff, repair options and replacement options discussed. TTC reached back out to Colombo for additional pricing on 12/31.
01/26/21 – Recommissioning cost never came back from Colombo, TTC woefully behind on final report to Bert. All work to be bid through this estimate, don’t use trades labor on this job.
02/24/21 – TTC needs to send final report with costs. Not done yet.
03/01/21 – ThermalTech sent Draft Report with costs to the County for review. The recommendation is to bid out the repair of the existing system replacing major equipment but all existing tubes can remain. Colombo sent in additional information for pricing today. TTC reached out with request for full replacement cost.
03/25/21 – Report complete and with the County, Facilities and Sheriff discussing next steps.
04/29/21 – Awaiting next steps.
05/24/21 – Colombo sent an email stating that the replacement carrier they had manufactured is ready for testing. I put us down for one at $350 when they are ready for public purchase.
05/27/21 – County reported the Sheriff has some movement on this project, TBD
06/25/21 – No updates from TTE this month.
07/28/21 – No updates.
08/26/21 – No updates.

10/28/21 – No updates. OK to archive.