PM: John Nester, Mike Barth
02/29/24 – Project created for tracking. MCB says we have all we need.
03/27/24 – Project docs to be sent to JN ASAP.
04/24/24 – BW and TEI review ODOT documents and submit what we can. Balance of data required from tenant.
05/29/24 – Project pending data from tenant.
06/26/24 – Project pending data from tenant.
07/24/24 – Project pending data from tenant.
08/28/24 – TEI and HCFD develop a package to send to ODOT for review and commentary including bid documents, project manual and OPC. Package sent to ODOT on 08/28/24.
09/25/24 – Project pending ODOT approval.
10/30/24 – Pending ODOT approval
12/11/24 – No Updates from ODOT.
01/29/25 – No updates from ODOT.
02/26/25 – No Updates from ODOT.
04/23/25 – Received Stage 3 approval from ODOT. HCFD investigating funding gap from the grant and the updated costs. Then notify TEI on next steps.
05/28/25 – Next steps to be coordinated with HCFD.
06/25/25 – TEI sends updated opinion of probable cost to HCFD for county to discuss grant funding/cost differential.
07/30/25 – No Updates
10/29/25 – DEG receives email from HCFD that this project is cancelled. OK to Archive.