A&D – JFS Furniture Redesign DD-CA

02/08/22 – Signed SOSS Received. Kickoff meeting scheduled for 03/22
03/22/22 – DD Kickoff meeting held. Weekly meetings scheduled for friday mornings for duration of DD phase.
04/13/22 – THP requested to review proposed cabinet layout on the fifth floor on the west side of the building.
04/14/22 – THP – Champlin approved THP proposal.
04/22/22 – Weekly DD meetings in progress.
04/26/22 – THP reviewed the cabinet location and analyzing the conditions.
04/28/22 – Kevin asked about dehumidification in the basement. ThermalTech to look at existing conditions and trending this area. Three months DD and three months CD; inclusion meeting during CD phase.
05/27/22 – Weekly DD meetings in progress.
06/30/22 – Weekly meetings complete. DD drawings to be submitted 7/1, DD estimate 7/8.
07/28/22 – Weekly CD User group meeting to start end of august.
08/23/22 – First weekly meeting scheduled for 8/26.
09/29/22 – CD ongoing. Last progress meeting scheduled for 9/30.
10/17/22 – ThermalTech conducted several field trips back to the building for final design
10/26/22 – LEED Checklist returned to Champlin from ThermalTech with comments and suggestions. Drawings, titleblocks, spec headers all being coordinated wth Champlin.
10/26/22 – Final Owner Review meeting scheduled for 10/28/22.
10/27/22 – Friday final owner review will be electronic review. Print three 11×17
12/15/22 – Project out to bid.
01/26/23 – Project still in bid phase. final addendum to be sent out next thursday. Bid opens 2/9.
02/14/23 – Bid opening – Universal is apparent low bidder
02/22/23 – Bid Review is scheduled for 3/3. Meeting rescheduled to two weeks from now. Furniture package is currently under review. Champlin has requested additional information from furniture vendor.
03/30/23 – Champlin sent Letter of Recommendation for Universal. County still deciding whether to move forward with contract with Universal.
04/27/23 – Universal answered several follow up questions. County is proceeding with awarding the bid to Universal. Contract is in progress.
05/25/23 – Monthly meetings with users scheduled.
06/29/23 – No update.
07/27/23 – No update.
08/31/23 – No update.
09/28/23 – No update.
10/25/23 – No update.
12/07/23 – No update.
02/29/24 – No update.
03/28/24 – No update.
04/25/24 – No update.
06/27/24 – No update.
08/29/24 – No update.
09/26/24 – No update.
10/30/24 – No update.
12/12/24 – No update.
01/30/24 – No update.
02/27/25 – OK to Archive.