PM: Matt Butz, Paul Bellman
06/03/25 – County, Kleingers and THP had a meeting to discuss scope of asphalt repair work.
07/24/25 – County and THP met to discuss project phasing.
07/30/25 – THP published preliminary opinion of probable cost for the project.
08/08/25 – THP published SOSS.
08/18/25 – County had kick off meeting with Tumlin, Champlin, THP, and Kleingers.
08/20/25 – County approved SOSS.
08/28/25 – Kleingers scheduled to survey the parking lot.
09/08/25 – Kleingers survey received
09/22/25 – Kleingers, THP, HC reviewed Courtyard lot for RFI #03 regarding overlay vs milling.
11/05/25 – THP, HC, and Tumlin reviewed milling conditions and full depth repair options.
11/14/25 – Kleingers provided updated striping plan.
11/18/25 – THP reviewed new asphalt in courtyard during heavy rain. Puddling and improper slope was observed on east portion of lot.
01/28/26 – No updates – weather pending.
02/26/26 – No updates – weather pending.
03/24/26 – No updates – Status of ponding in Courtyard area?
04/30/26 – THP to review on site conditions.
05/28/26 – No updates. Work in adjacent areas ongoing.
06/25/26 – Sink hole and active line was discovered in Courtyard lot. THP, Davies, and HC discussed scoping, filling void, and providing cleanout per supplied detail. Tumlin to get CO cost to repair.
07/30/26 – No updates from THP. Have not heard from Tumlin on the CO costs to repair sink hole in Courtyard Lot.
09/23/26 – No updates.
10/29/26 – No updates. Punchlist coming and cleanout addressed soon.