PM: Rycca Thacker, John Millar
05/06/25 – County approved SOSS.
05/23/25 – County and THP had a kick off meeting.
08/28/25 – THP anticipates sending bid documents to contractors on 8/29/25.
09/02/25 – THP issued bid documents to American Façade Restoration, Buckeye Concrete Restoration, Hardig Industrial Services, and ZSR Contracting and Restoration. Kestner was unresponsive.
09/09/25 – Site prebid meeting occurred.
09/17/25 – Bids were received from three contractors. American Façade Restoration was the low bidder.
09/19/25 – THP reviewed the proposal with American Façade Restoration.
09/22/25 – THP published the a recommendation for American Façade Restoration to complete the work for the County to review.
09/24/25 – County requested additional bidders from the Bold list be invited to bid the project.
09/25/25 – THP sent three additional requests out to BSBE and MBE firms.
10/03/25 – THP received one proposal from LRT that was $15,000 over the low bidder.
10/15/25 – County issued a PO for AFR to complete the work.
10/29/25 – AFR is working through background checks. AFR is proposing to complete the work 11/10 to 11/14. Work is weather dependent and second shift.
12/11/25- THP has completed the survey at the building and is working on providing a City report regarding the observation by next week.
01/18/26 – The report has been approved by HC and THP submitted the report to the city.
04/30/26 – OK to archive this project.