PM: Matt Butz, Mike Barth
10/30/25 – Project was sent out for bid, DK sent in questions with options. Security lighting prebid also held.
12/10/25 – Project small projects bids received. Glenwood awarded the bid. Contract in finalization phase. Submittals and construction to commence once the contracts are approved.
01/28/26 – Project contracts and PO sent to subs. Meeting dates for KO meeting requested from contractor.
02/25/26 – DEG and HCFD meet with Glenwood on exterior lighting. Installation of drawings pending light fixture procurement (approx mid March).
03/25/26 – Exterior lighting installed. Play yard lighting levels requested to be increased. DEG performs lighting study to increase the lighting levels. DEG sends to HCFD.
04/29/26 – Play yard lights installed last week. All exterior lighting complete. Security cameras work to commence upon the completion of Central Campus work.
05/27/26 – Play yard lights permitted and inspected (final inspection passed). Cameras are kicking off beginning of June.
06/23/26 – DK has mobilized to the project site to install the cameras. installation is underway. Weekly project meetings scheduled.
07/29/26 – Installation underawy. Most of access control installed. Cameras are being installed and cabling installed with the GSA vendor.
08/26/26 – Installation will be finalized when ISWP installed at the location.
09/23/26 – ISWP installed by technical services. Installation finalization and connections scheduled with DK.
10/28/26 – Installation of cameras nearing completion.