PM: Megan, Sam
10/30/25 – This project went out to bid this week. Sam will send out invites for prebid and bid opening.
12/11/25 – Triton is low bidder. Project in contract phase.
12/12/25 – Furniture and two drawer cabinets can be located close to the hot water radiators, they just have to be moved if we ever need to service the units.
01/28/26 – Contract goes in front of the board today. Bulletin #1 will go out next week with the changes requested from Rycca.
02/26/26 – Contract is signed. Triton is to pace projects out to place priority on Bondhill. Submittals and pre-mob items can begin.
03/26/26 – No update.
04/30/26 – Submittals are coming in. Project mobilization to be scheduled by County.
05/28/26 – Project tentative start on 8/10/26.
06/25/26 – No update.
07/30/26 – Submittals are being returned. Project start has adjusted to 8/31.
07/30/26 – RT said we may get new direction on final design for this space. We may need another Bulletin for this project.
08/28/26 – Mobilization on hold until scope changes are settled.
09/24/26 – Scope changes received. Bulletin is being prepared.
10/29/26 – Bulletin will be issued to Triton upon approval