All Buildings – Emergency Switchgear PM

PM: Rycca Thacker, Mike Barth
10/30/25 – The project is out for bid, prebid is scheduled for November.
12/10/25 – Bid opening occurred. Zero bids received.
01/28/26 – HamCo asks DEG to re-package and resend out to bid.
02/25/26 – No updates this month. DEG will compile all data and send list of buildings that information is still pending.
06/23/26 – DEG contacts all building managers to confirm that there have been no modifications to the critical load lists for each building. A review set will be sent to HCFD end of June.
07/29/26 – DEG has not received responses from buildings.
08/26/26 – ITB pending the advertised estimate from HCFD and then goal setting worksheet approval.
09/23/26 – Project in bidding phase. Prebid meeting was held on 09/22. Bids are due 11/12/26.
10/28/26 – Project in bidding phase. (2) Addendums Issued.